Examples of Guaranteed Substantial Completion Dates in a sentence
All Change Order Requests shall include documentation sufficient to enable Owner to determine: (a) the factors necessitating the possibility of a Change; (b) the impact which the Change is likely to have on the Contract Price; (c) the impact which the Change is likely to have on the timely achievement of the activities set forth in the Project Schedule (including the Guaranteed Substantial Completion Dates); and (d) such other information which Owner may request in connection with such Change.
Similarly, to the extent that a Change enhances Contractor's or its Subcontractors' ability to perform the Work, reduces the cost of the Work or its other obligations under this Agreement, or shortens the Project Schedule, Owner shall be entitled to an equitable adjustment as appropriate to the Contract Price, the Project Schedule, the Milestone Payment Schedule, the Guaranteed Substantial Completion Dates, the Scope of Work and/or such other parts of this Agreement as may be affected by such Change.
Under Article 9, the Contractor is entitled to an adjustment to the Project Schedule, the Payment Schedules, the Guaranteed Substantial Completion Dates, the Critical Milestones and such other provisions of the EPC Agreement affected by the Change.
If the Parties do not agree on the effects of a Owner/Authority-requested change in the Work on the Contract Price or the Guaranteed Substantial Completion Dates or on any other provision hereof, Contractor shall, if directed by Owner and Authority pursuant to a written instruction, nevertheless proceed to perform such change in the Work, subject to Contractor’s dispute rights under Section 8.3.
Once the event that allowed Contractor to suspend Work under this Section 22.4(a) has occurred, Owner and Contractor shall negotiate a Change in the Contract Price, Project Schedule (including the Guaranteed Substantial Completion Date(s)), and such other applicable terms and conditions of this Agreement to reflect the effect of such event, including, without limitation, the suspension of the Work, and the demobilization and remobilization of Contractor's and the Subcontractors' forces, as applicable.
Similarly, the Guaranteed Substantial Completion Dates for Power Blocks 1 and 2 were revised to August 1, 2018 and November 1, 2018, respectively.
Unless otherwise mutually agreed upon by the Parties, Contractor shall revise and update the Project Schedule quarterly prior to the commencement of on-Site construction work and monthly thereafter and shall provide a copy to Owner, which may be provided electronically; provided, however, that the Guaranteed Substantial Completion Dates for the Units shall not be revised other than pursuant to Article 9.
Contractor’s failure to acquaint itself with any general or local condition or circumstances affecting the Work existing as of the date of this Agreement will neither relieve it from the responsibility for successfully performing this Agreement, nor entitle Contractor to an adjustment to the Contract Price or the Guaranteed Substantial Completion Dates.
The very next day, July 1, 2016, Marsh and Byrne submitted written testimony to the PSC in support of SCANA’s petition that the PSC adopt August 2019 and August 2020 as the Guaranteed Substantial Completion Dates for Unit 2 and Unit 3 and approve the fixed price option.
Projected substantial completion dates do not reflect the October 2015 Amendment to the Guaranteed Substantial Completion Dates for Units 2 and 3.