Initial Span definition

Initial Span means the number of Charged Days bid by the Contractor for Site Occupancy on Form B: Prices;

Examples of Initial Span in a sentence

  • Initial Span: Means the number of Charged Days bid by the Contractor for Site Occupancy on Form B: Prices.

  • Site Occupancy Costs shall be the Initial Span bid in the Charged Days, multiplied by the Site Occupancy Unit Price listed in Form B: Prices.

  • Technical personnel (to include Government SMEs, e.g., system safety, security, IA) should participate on each panel (or committee) of the source selection organization (see Figure 2­3), as necessary to assess each factor and subfactor that forms the basis of the source selection.

  • A., “The Effect of Initial Span on the Measured Tensile Properties of Paper,” Tappi 47 (1): 47 (1964).

  • RBH is expected to recover the position from the end of April 2013 and is on track to meet its trajectory.Imperial College Healthcare NHS Trust (ICHT) – ICHT continues to achieve all 18 week RTT standards overall however it did not meet the admitted, non-admitted and incomplete pathway standards across five specialties (General Surgery, ENT, Orthopaedics, Plastic Surgery, and Urology).

  • PRICES B10.1 The Bidder shall state a price in Canadian funds for each item of the Work identified on Form B: Prices.B10.1.1 The Bidder must complete the Approximate Quantity column for item I1 Initial Span on Form B: Prices in accordance with D23.B10.1.2 Prices stated on Form B: Prices shall not include any costs which may be incurred by the Contractor with respect to any applicable funding agreement obligations as outlined in D35.

  • B10.2 The Bidder must complete the Approximate Quantity column for item J1 Initial Span on Form B: Prices in accordance with D24 B10.3 The quantities listed on Form B: Prices are to be considered approximate only.

  • The Contractor shall provide the necessary material, labour and equipment to ensure that the Work will be completed within the consecutive amountof Charged Days Bid for Initial Span for Site Occupancy, and in no case later than the date specified for Total Performance.

  • The Initial Span should not include the completion of Provisional Items (Part B, Form B: Prices).

  • E27.4 Provisional Items do not form part of the Initial Span calculations.PART F - SECURITY CLEARANCE F1.