Therefore, if we do not have a formal program in place addressing work environment issues, little will change.” The parties will work together in the development of an Initial Work Plan that will move towards the Healthy Work Environment envisioned by AACN.
Expected Outputs:• Initial Work Plan: A planning document that identifies key players, project constraints, core components, scope of testing, and level of expected rigor.
Initial Work Plan ScheduleThe Initial Work Plan (IWP) Schedule is a time-scaled CPM schedule showing detailed activities for the first 90 calendar days of work and summary level activities for the remainder of the project.
Subsection C, IV, 5 of the Task Order requires Parsons to establish an Initial Work Plan that addresses quality-assurance methods, organizational updates, and changes to the plan within five days of receiving the Notice to Proceed (NTP).Parsons completed this Work Requirement during the June Progress Reporting period.
Subsection C, IV, 13 of the Task Order requires Parsons to establish an Initial Work Plan that addresses quality-assurance methods, organizational updates, and changes to the plan within five days of receiving the Notice to Proceed (NTP).See response to Work Requirement #5.Parsons completed this Work Requirement during the June Progress Reporting period.
Replace standard spec 108.4 with the following: 108.4 Critical Path Method Progress Schedule108.4.1 SoftwareUse the latest version of Oracle (Primavera) Project Manager (P6) version 7.0 or newer to prepare the Initial Work Plan Schedule, Baseline CPM Progress Schedule, and all Monthly CPM Updates.
This Initial Work Plan will provide the case plan that will be refined during the Preparatory Period (first 30 days of the engagement).20 pointsCost: Ongoing costs must be affordable to PBCHA within the administrative fee structure of the Housing Choice Voucher Program.
For the avoidance of doubt, Hovione’s final invoice for each phase of the Initial Work Plan shall serve as written notification to Client of the completion of that phase of the Initial Work Plan.
Use the latest version of Primavera Project Planner (P6), by Primavera Systems, Inc., Bala Cynwyd, PA to prepare the Initial Work Plan, Baseline CPM Progress Schedule, and Monthly CPM Updates.
Initial Work Plan Adjustments and Project Start DateAlthough the Year 1 Work Plans are deemed to be satisfactory, the seven consortia grantees approved by this resolution must work with CD staff to fine-tune their work plans and submit final documents within 15 days of the approval of this resolution.Once CD approves the modifications, then the start date can commence in January.