Outside Construction Commencement Date definition

Outside Construction Commencement Date means the later of ninety (90) days after the Effective Date or ninety (90) days after the PV System has received a “Statement of Qualificationpursuant to and as defined in the SMART Program or ninety (90) days after PV System has received all permits or approvals from the distribution company or approval board or any governmental authority.
Outside Construction Commencement Date means the later of ninety (90) days after the Effective Date or ninety (90) days after Developer receives notification from DOER that DOER has issued a final Statement of Qualifications approving the developer’s enrollment in the SMART Program.
Outside Construction Commencement Date means March 31, 2008, extended one day for each day of Sublessee Delay identified and occurring prior to March 31, 2008, but not extended for delays resulting from Force Majeure.

Examples of Outside Construction Commencement Date in a sentence

  • If commencement of construction does not occur on or before the Outside Construction Commencement Date and/or Commercial Operation does not occur on or before the Outside Commercial Operation Date for any reason other than User’s failure to perform its obligations hereunder, Contractor shall pay to User lost revenues plus User’s administrative costs as the basis for damage (“Delay Liquidated Damages”), as set forth in the Special Terms and Conditions attached as Exhibit F.

  • Payment of Delay Liquidated Damages shall not preclude User from seeking other damages at law or equity to which it may be entitled as a result of Contractor’s failure to achieve commencement of construction on or before the Outside Construction Commencement Date and/or Commercial Operation on or before the Outside Commercial Operation Date.

  • Notwithstanding the foregoing, Contractor shall not be responsible for Delay Liquidated Damages in the event that Contractor cannot satisfy the Outside Construction Commencement Date and/or Outside Commercial Operation Date milestone because Contractor lacks a permit, approval or Interconnection Agreement necessary to commence construction and/or Commercial Operation of the PV System, and Contractor is utilizing Commercially Reasonable efforts to secure such permit, approval or Interconnection Agreement.


More Definitions of Outside Construction Commencement Date

Outside Construction Commencement Date. Ten (10) days after the Commencement Date.
Outside Construction Commencement Date means one hundred eighty (180) days after the Effective Date, subject to any extension of such period due to delays caused by or requirements under any agreement required for the interconnection of the System with the LDC or any landfill closure plan.
Outside Construction Commencement Date means that date which is thirty (30) days after the Closing Date.
Outside Construction Commencement Date means that date which is sixty (60) days after the Closing Date.
Outside Construction Commencement Date means one hundred eighty (180) days after the Effective Date for a roof mounted PV System and three hundred (300) days after the Effective Date for a ground mounted PV System.
Outside Construction Commencement Date means the Outside Construction Commencement Date set forth in the Milestone Schedule set forth in Exhibit F.
Outside Construction Commencement Date means [ ], as such date may be extended in accordance with Section 2.b.