Provisional Sum Item definition

Provisional Sum Item means an item of work (including a measure to be adopted in respect of a Pandemic Outbreak) which shall only be executed or provided upon instruction in writing by the Employer, who may decide that the work in whole or in part or not at all may be carried out by the Consultant.
Provisional Sum Item means an item of work (including labour and materials) for which the Builder, after making all reasonable inquiries, cannot give a definite price at the time that this Contract is entered into and which the Builder has made allowance for in the Contract Price.
Provisional Sum Item means an item described as such at Item 8 .

Examples of Provisional Sum Item in a sentence

  • If the actual cost of a Prime Cost Item or Provisional Sum Item is less than the Contractor’s estimate, the Contractor must deduct the difference, plus the margin, from the Contract Price.

  • If the invoiced cost to the Contractor of a Provisional Sum Item exceeds or is less than the relevant Provisional Sum, the difference is to be added to or deducted from the Contract Sum as the case may require.

  • If, at the direction of the Supervising Officer under sub-clause 5.1(b) or by reason of the operation of clause 5.2, a Provisional Sum Item is deleted from the Services, the Fee must be reduced by the Provisional Sum corresponding to that Provisional Sum Item.

  • If the Supervising Officer has not given the Consultant a direction in respect of a Provisional Sum Item under clause 5.1 by the Date for Completion, then the Provisional Sum Item will be deemed to be deleted from the Services.

  • Where the Contractor is instructed by the Superintending Officer to execute or provide some or all of the Plant, materials, goods or work described as a Provisional Sum Item, the valuation relating to the instruction shall be in accordance with Clause 20.1 (unless otherwise provided in this Contract).

  • Where the Contractor is instructed by the Superintending Officer to execute or provide some or all of the Plant, materials, goods or work described as a Provisional Sum Item, the valuation of that instruction shall be made in accordance with Clause 20.1 (unless otherwise provided in this Contract).

  • Provisional Sum Items For each Provisional Sum Item, the Supervising Officer must give the Consultant a direction either: requiring the Consultant to perform the relevant Provisional Sum Item; or deleting it from this Agreement.

  • If the actual cost for a Provisional Sum Item is less than the Contractor’s estimate in the Provisional Sums Schedule, the Contractor must deduct the difference, plus the Contractor’s margin, from the Contract Price.

  • Provisional Sum Adjustments A Provisional Sum included in this Agreement is not itself payable by the Department but where, at the direction of the Supervising Officer under sub-clause 5.1(a), a Provisional Sum Item is performed or supplied by the Consultant, then the Fee must be adjusted by the deletion of the Provisional Sum to which the Provisional Sum Item relates and then by the addition of an amount agreed by the parties or, where not so agreed, as valued under clause 11.12.


More Definitions of Provisional Sum Item

Provisional Sum Item means the services, activities, works or items described in part C of Schedule 2. Public Sector Employee has the same meaning as set out in section 4 of the Public Administration Act 2004 (Vic).