Examples of Tidewater Virginia in a sentence
For projects that disturb 10,000 square feet or greater of land or 2,500 square feet or greater in Tidewater, Virginia, the Contractor shall have within the limits of the project during land disturbance activities, an employee certified by the Department in erosion and sediment control who shall inspect erosion and sediment control and pollution prevention practices, devices and measures for proper installation and operation and promptly report their findings to the Inspector.
Because the 84 local governments within Tidewater Virginia are responsible for enforcing the CBPA Regulations, the completion of the JPA process does not constitute compliance with the Bay Act Regulations nor does it guarantee that the local government will approve encroachments into the RPA that may result from this project.
The board encourages applicants to coordinate the determination of perennial or nonperennial streams with the appropriate local government agency in Tidewater Virginia.
Any “No Plan” project that disturbs 2,500 square feet (232 m2) or greater in Tidewater, Virginia or 10,000 square feet (929 m2) or greater elsewhere within the State must have a project specific ESC Plan.
Any “SAAP” project that disturbs 2,500 square feet (232 m2) or greater in Tidewater, Virginia or 10,000 square feet (929 m2) or greater elsewhere within the State must have a project specific ESC Plan.
Any maintenance or construction activity disturbing 2,500 square feet (232 m2) or greater within the area of Tidewater, Virginia, as defined in the Virginia Chesapeake Bay Preservation Act, must have a project specific ESC Plan developed and implemented in accordance with the VDOT’s Approved ESC Standards and Specifications.
The SWPPP is comprised of, but not limited to, the Erosion and Sediment Control (ESC) Plan, the Stormwater Management (SWM) Plan and related Specifications and Standards contained within all contract documents and shall be required for all land-disturbing activities that disturb 10,000 square feet or greater, or 2,500 square feet or greater in Tidewater, Virginia.
Any maintenance or construction activity disturbing 10,000 square feet (929 m2) or greater in areas other than those within Tidewater, Virginia (as defined in Section 4.3 of this document) must have a project specific ESC Plan developed and implemented in accordance with VDOT’s Approved ESC Standards and Specifications.
Regulated land disturbing activities are defined as those activities that disturb 2,500 square feet or greater in Tidewater, Virginia or 10,000 square feet or greater in all other areas of the State.
Section 107.16 (e) of the 2007 VDOT R&B Specifications requires all land disturbance activities that disturb 10,000 square feet or greater (2500 square feet or greater in the area defined as Tidewater, Virginia in the Chesapeake Bay Preservation Act) (see the latest version of IIM-LD-11) to have a SWPPP.