Extended force majeure Mallilausekkeet

Extended force majeure. If force majeure or repeated force majeure situations are expected to impede in full or in part the fulfilment of a Party’s obligations for a period of more than sixty (60) Business Days, the Parties shall seek a negotiated solution acceptable to the Parties. If the Parties are unable to agree on a solution within thirty (30) Business Days after a request has been made for a negotiated solution, the Party or Parties having claimed force majeure are entitled to terminate the Agreements (Capacity Agreements and/or this Framework Agreement) affected by the force majeure situation. For the avoidance of doubt, it is noted that the existence of force majeure is determined in relation to the time of inception of the contractual relationship. 17 Compensation for damage‌