A/E’s Submittal Review. The A/E shall review submittals for conformity with design intent within 14 days of receiving them or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and the Contractor. The A/E’s review of submittals is to determine if the items covered by the submittals will, after installation and incorporation into the Work, conform to the Contract Documents and be compatible with the design concept of the Project as a functioning whole. 6.20.5.1 The Contractor shall make corrections required by the A/E and resubmit the required number of corrected copies of submittals until approved, which resubmission shall be acted upon by the A/E within 14 days of receiving them, or other period as is mutually agreed by the A/E and the Contractor. 6.20.5.2 When resubmitting corrected submittals, the Contractor shall direct the A/E’s attention to revisions made by noting revisions on the resubmittal. 6.20.5.3 The Contractor shall pay all reasonable costs of the A/E, the Owner, and the Contracting Authority for attendant delay, interference, hindrance or disruption of the Project due to excessive resubmittals without fault of the A/E, the Owner, or the Contracting Authority. Resubmittals in excess of 2 without fault of the A/E, the Owner, or the Contracting Authority may be determined excessive by the Contracting Authority. 6.20.5.4 The A/E may hold Samples and other submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that the submittal is being held, within 7 days of receiving it. 6.20.5.5 If coordinating submittals are not received within the period required for action on previously received submittals that are held in accordance with Section 6.20.5.46.20.5.4, review of the previously received submittals shallmay be delayed. 6.20.5.6 The A/E’s review shall not extend to means, methods, manners, techniques, sequences, noror procedures of construction, or to safety precautions or incident programs. 6.20.5.7 The review and approval of a separate item shall not indicate approval of the assembly in which the item functions.
Appears in 2 contracts
Samples: General Contracting Agreement, Standard Requirements for Public Facility Construction
A/E’s Submittal Review. The A/E shall review submittals for conformity with design intent within 14 days of after receiving them or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and the ContractorCM. The A/E’s review of submittals is to determine if the items covered by the submittals will, after installation and incorporation into the Work, conform to the Contract Documents and be compatible with the design concept of the Project as a functioning whole.
6.20.5.1 6.18.5.1 The Contractor CM shall make corrections required by the A/E and resubmit the required number of corrected copies of submittals until approved, which resubmission shall be acted upon by the A/E within 14 days of after receiving them, or other period as is mutually agreed by the A/E and the ContractorCM.
6.20.5.2 6.18.5.2 When resubmitting corrected submittals, the Contractor CM shall direct the A/E’s attention to revisions made by noting revisions on the resubmittal.
6.20.5.3 6.18.5.3 The Contractor CM shall pay all reasonable costs of the A/E, the Owner, and the Contracting Authority for attendant delay, interference, hindrance hindrance, or disruption of the Project due to excessive resubmittals without fault of the A/E, the Owner, or the Contracting Authority. Resubmittals in excess of 2 two without fault of the A/E, the Owner, or the Contracting Authority may be determined excessive by the Contracting Authority.
6.20.5.4 6.18.5.4 The A/E may hold Samples and other submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until submittals for adjacent materials are available. The Within seven days after receiving the submittal, the A/E shall issue a written notice to the Contractor CM stating that the submittal is being held, within 7 days of receiving it.
6.20.5.5 6.18.5.5 If coordinating submittals are not received within the period required for action on previously received submittals that are held in accordance with Section 6.20.5.46.20.5.46.18.5.4, review of the previously received submittals shallmay may be delayed.
6.20.5.6 6.18.5.6 The A/E’s review shall not extend to means, methods, manners, techniques, sequences, noror or procedures of construction, or to safety precautions or incident programs.
6.20.5.7 6.18.5.7 The review and approval of a separate item shall not indicate approval of the assembly in which the item functions.
Appears in 2 contracts
Samples: Professional Services, Construction Manager at Risk Agreement
A/E’s Submittal Review. The A/E shall review submittals for conformity with design intent within 14 days of receiving them or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and the Contractor. The A/E’s review of submittals is to determine if the items covered by the submittals will, after installation and incorporation into the Work, conform to the Contract Documents and be compatible with the design concept of the Project as a functioning whole.
6.20.5.1 The Contractor shall make corrections required by the A/E and resubmit the required number of corrected copies of submittals until approved, which resubmission shall be acted upon by the A/E within 14 days of receiving them, or other period as is mutually agreed by the A/E and the Contractor.
6.20.5.2 When resubmitting corrected submittals, the Contractor shall direct the A/E’s attention to revisions made by noting revisions on the resubmittal.
6.20.5.3 The Contractor shall pay all reasonable costs of the A/E, the Owner, and the Contracting Authority for attendant delay, interference, hindrance or disruption of the Project due to excessive resubmittals without fault of the A/E, the Owner, or the Contracting Authority. Resubmittals in excess of 2 without fault of the A/E, the Owner, or the Contracting Authority may be determined excessive by the Contracting Authority.
6.20.5.4 The A/E may hold Samples and other submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that the submittal is being held, within 7 days of receiving it.
6.20.5.5 If coordinating submittals are not received within the period required for action on previously received submittals that are held in accordance with Section 6.20.5.46.20.5.46.20.5.4, review of the previously received submittals shallmay may be delayed.
6.20.5.6 The A/E’s review shall not extend to means, methods, manners, techniques, sequences, noror or procedures of construction, or to safety precautions or incident programs.
6.20.5.7 The review and approval of a separate item shall not indicate approval of the assembly in which the item functions.
Appears in 1 contract
Samples: Standard Requirements for Public Facility Construction
A/E’s Submittal Review. The A/E shall review submittals for conformity with design intent within 14 days of receiving them or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and the ContractorCM. The A/E’s review of submittals is to determine if the items covered by the submittals will, after installation and incorporation into the Work, conform to the Contract Documents and be compatible with the design concept of the Project as a functioning whole.
6.20.5.1 The Contractor CM shall make corrections required by the A/E and resubmit the required number of corrected copies of submittals until approved, which resubmission shall be acted upon by the A/E within 14 days of receiving them, or other period as is mutually agreed by the A/E and the Contractor.CM. Version Control Document
6.20.5.2 When resubmitting corrected submittals, the Contractor CM shall direct the A/E’s attention to revisions made by noting revisions on the resubmittal.
6.20.5.3 The Contractor CM shall pay all reasonable costs of the A/E, the the, Owner, and the Contracting Authority for attendant delay, interference, hindrance or disruption of the Project due to excessive resubmittals without fault of the A/E, the Owner, or the Contracting Authority. Resubmittals in excess of 2 without fault of the A/E, the Owner, Owner or the Contracting Authority may be determined excessive by the Contracting Authority.
6.20.5.4 The A/E may hold Samples and other submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor CM stating that the submittal is being held, within 7 days of receiving it.
6.20.5.5 If coordinating submittals are not received within the period required for action on previously received submittals that are held in accordance with Section 6.20.5.46.20.5.46.20.5.4, review of the previously received submittals shallmay be delayed.
6.20.5.6 The A/E’s review shall not extend to means, methods, manners, techniques, sequences, noror or procedures of construction, or to safety precautions or incident programs.
6.20.5.7 The review and approval of a separate item shall not indicate approval of the assembly in which the item functions.