Annual Planned Maintenance Schedule. 2.1 Not later than six (6) Months prior to the commencement of each Contract Year (save for the first year of Operation of the Facility Unit, for which the corresponding period shall be forty (40) Business Days prior to the Commercial Operation Date), the Seller shall submit its Scheduled Outages for that year following consultation with the Buyer regarding the Buyer's anticipated major Maintenance Outages in that calendar year. 2.2 The Buyer may on not less than forty (40) Business Days' prior written notice to the Seller, request the Seller to reschedule a Scheduled Outage to an alternative Month and the Seller shall use all reasonable endeavours to accommodate such rescheduling if it is consistent with the standards of a Reasonable and Prudent Operator. 2.3 The Seller may on no less than twenty (20) Business Days' prior written notice to the Buyer reschedule a Scheduled Outage to an alternative Month; provided that such rescheduling is consented to in writing by the Buyer, which consent may not be unreasonably withheld.
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Annual Planned Maintenance Schedule. 2.1 Not later than six (6) Months prior to the commencement of each Contract Year (save for the first year of Operation of the Facility UnitFacility, for which the corresponding period shall be forty (40) Business Days prior to the Commercial Operation Date), the Seller shall submit its Scheduled Outages for that year following consultation with the Buyer regarding the Buyer's anticipated major Maintenance Outages in that calendar year.
2.2 The Buyer may on not less than forty (40) Business Days' prior written notice to the Seller, request the Seller to reschedule a Scheduled Outage to an alternative Month and the Seller shall use all reasonable endeavours to accommodate such rescheduling if it is consistent with the standards of a Reasonable and Prudent Operator.
2.3 The Seller may on no less than twenty (20) Business Days' prior written notice to the Buyer reschedule a Scheduled Outage to an alternative Month; provided that such rescheduling is consented to in writing by the Buyer, which consent may not be unreasonably withheld.
Appears in 1 contract
Samples: Power Purchase Agreement