Common use of Application of Generator Interconnection Procedures Clause in Contracts

Application of Generator Interconnection Procedures. Sections 2 through 13 apply to processing an Interconnection Request pertaining to a Generating Facility interconnecting to the Transmission System. 2.1.1 Transmission Provider may modify the technical information required for an Interconnection Request for a Generating Facility with a capacity of 20 MW or less. The scope of work for Interconnection Studies for a