Payment Requests Review applications for payment with Contractor for compliance with the established procedure for their submission and forward with recommendations to Engineer, noting particularly the relationship of the payment requested to the schedule of values, Work completed, and materials and equipment delivered at the Site but not incorporated in the Work.
Waiver of Notice; Approval of Meeting; Approval of Minutes The transactions of any meeting of Limited Partners, however called and noticed, and whenever held, shall be as valid as if it had occurred at a meeting duly held after regular call and notice, if a quorum is present either in person or by proxy. Attendance of a Limited Partner at a meeting shall constitute a waiver of notice of the meeting, except when the Limited Partner attends the meeting for the express purpose of objecting, at the beginning of the meeting, to the transaction of any business because the meeting is not lawfully called or convened; and except that attendance at a meeting is not a waiver of any right to disapprove the consideration of matters required to be included in the notice of the meeting, but not so included, if the disapproval is expressly made at the meeting.
PROGRESS PAYMENT 9.2.1 City shall retain five percent (5%) of the undisputed amount due on each progress payment, or the percentage stated in the Notice Inviting Bids, whichever is greater, as retention to ensure full and complete performance of the Work. Subject to City’s right of withholding under Paragraph 9.4.2 of these General Conditions, City agrees to pay to Contractor within thirty (30) Days of receipt of a properly submitted Application for Payment an amount equal to ninety-five percent (95%), or a lesser amount if corresponding to a higher retention percentage, if applicable, of the sum of the following, excepting therefrom any amounts which are disputed by City: (i) Construction Manager’s determination of the value, expressed as a percentage of the Contract Sum, of the Work in permanent place that has been tested and accepted as of the end of the preceding month. (ii) Construction Manager’s determination of the value of materials suitably stored but not yet incorporated into the Work, subject to Paragraph 9.3.6 of these General Conditions. (iii) Less amounts previously paid. 9.2.2 At any Time after fifty percent (50%) of the Work has been determined by Construction Manager to be completed, City may in its sole discretion, make any of the remaining progress payments in accordance with the calculation in Paragraph 9.2.1 of these General Conditions based on one hundred percent (100%) of City’s determination of the value of the Work in place and of stored materials not yet incorporated into the Work. 9.2.3 Progress payments shall not be construed as City's Acceptance of any or all of the Work and shall not be a waiver of any or all rights City has under the Contract Documents.
Progress Payments 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
Application for approval 3.1. The application for approval of a vehicle type with regard to the AEBS shall be submitted by the vehicle manufacturer or by his authorised representative. 3.2. It shall be accompanied by the documents mentioned below in triplicate: 3.2.1. A description of the vehicle type with regard to the items mentioned in paragraph 2.4., together with a documentation package which gives access to the basic design of the AEBS and the means by which it is linked to other vehicle systems or by which it directly controls output variables. The numbers and/or symbols identifying the vehicle type shall be specified. 3.3. A vehicle representative of the vehicle type to be approved shall be submitted to the Technical Service conducting the approval tests.
New Application for Licensure Any time after the three-month period has lapsed from the Effective Date of this Agreement and Respondent has paid the Administrative Penalty set forth in Section III, Paragraph 1 of this Order, Respondent may apply for a new mortgage loan originator license or, as applicable, petition for the reinstatement of an MLO Activity Endorsement in any or all of the Participating States with the understanding that each State Mortgage Regulator reserves the rights to fully investigate such application for licensure or petition for reinstatement of an MLO Activity Endorsement and may either approve or deny such application or petition pursuant to the normal process for such licensing or endorsement investigations. No license application or petition described in this paragraph will be denied solely based on the facts, circumstances, or consensual resolution provided for in this Agreement. Respondent further agrees that Respondent must satisfy the Administrative Penalty provision prior to submitting an application for a new mortgage loan originator license or, as applicable, petition for the reinstatement of an MLO Activity Endorsement.
PROGRESS AND COMPLETION 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract. 8.2.2 The Contractor shall begin the Work on the date of commencement as defined in 8.2.3 If in the sole opinion of the State, the Contractor fails to commence work on the project or to complete the work of said project within the time specified above, or to prosecute the work in such a manner that it appears that the completion date can be assured, the State shall have the right to notify the Contractor by Certified Mail that the terms of the Contract have been violated, and that effective immediately the Contract is terminated and the State has the right to and in fact is taking over and attending to completion of the project without prejudice to the State's remedies for any losses sustained
Stop Payment Requests If you desire to stop any transfer that has already been processed, you must contact customer care for the Service pursuant to Section 22 of the General Terms. Although we will make a reasonable effort to accommodate your request, we will have no liability for failing to do so. We may also require you to present your request in writing within fourteen (14) days. The charge for each request will be the current charge for such service as set out in the applicable fee schedule.
Development Milestone Payments (i) In addition to the Closing Date Merger Consideration (less the Remaining Option Consideration and Rights Proceeds Amount, if any) and any Net TNF Sales Payments (as defined below), upon the attainment of the development ** Portions of the Exhibit have been omitted and have been filed separately pursuant to an application for confidential treatment filed with the Securities and Exchange Commission pursuant to Rule 24b-2 under the Securities Exchange Act of 1934, as amended. milestones set forth below (each, a “Development Milestone”), Parent shall, or shall cause the Surviving Corporation to, [**] after the occurrence of each Development Milestone, deliver to the Paying Agent (for further payment to the holders of Stock Certificates and Stock Agreements outstanding immediately prior to the Effective Time), via wire transfer of immediately available funds, the respective amounts set forth below minus, in each case, the applicable Contingent Consideration Distribution Fee associated therewith and any amount designated by the Stockholders’ Representatives to be placed in the Administrative Expense Account (each, a “Development Milestone Payment” and collectively, the “Development Milestone Payments”): (A) Upon FDA approval of Reslizumab for the treatment of eosinophilic esophagitis, a cash payment of [**]; (B) Upon marketing authorization of Reslizumab for the treatment of eosinophilic esophagitis being granted by the European Commission in accordance with Regulation (EC) No. 726/2004, a cash payment of [**]; (C) If Res 5-0010 Asthma Study Completion has not occurred on or prior to the Closing Date, then upon the occurrence of the Res 5-0010 Asthma Study Completion, a cash payment of $50,000,000 (fifty million dollars) (the “Res 5-0010 Asthma Payment”); (D) Upon FDA approval of Reslizumab for any asthma indication, a cash payment of [**]; (E) Upon marketing authorization of Reslizumab for the treatment of any asthma indication being granted by the European Commission in accordance with Regulation (EC) No. 726/2004, a cash payment of [**]; and (F) Upon FDA approval of an Oral Anti-TNF Product, a cash payment of [**].