Approval of the Schedule of Values Sample Clauses

Approval of the Schedule of Values. (a) Approve any change, modification or supplement to the “Schedule of Values” in effect on the Closing Date for the Phase I Project pursuant to Section 5.1 of the Phase I Primary Construction Contract or approve the initial “Schedule of Values” (or comparable provision) for the Phase II Project under the Phase II Primary Construction Contract, or any change, modification or supplement thereto, without, in each case, the consent of the Construction Consultant or (b) fail to direct any Primary Contractors to adjust the Schedule of Values for any portion of the Projects as contemplated in the last sentence of Section 5.1 of the Phase I Primary Construction Contract or any similar provision of the Phase II Primary Construction Contract as and when required by the Construction Consultant.
AutoNDA by SimpleDocs

Related to Approval of the Schedule of Values

  • Schedule of Values 9.2.1 Before the first Application for Payment, the Contractor shall submit to the Architect a schedule of values allocated to the various portions of the Work, prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used only as a basis for the Contractor's Applications for Payment.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Pay Schedule 50.01 The regularly scheduled pay day shall be bi-weekly, every other Friday. Pay shall be by direct deposit to the employee’s financial institute as on record with the Employer, with an electronic pay statement issued to the employee on or before the pay date. 50.02 The employee’s pay stub shall be delivered to the employee’s workplace and distributed to the employee on or before the specified pay date. 50.03 Employees shall be paid in accordance with Schedule “A” of this agreement.

  • Wage Schedule ‌ The pay rate (including increments and stated extras) as agreed to and hereinafter in this Schedule provided, shall be in effect during the term of the Agreement, from April 1, 2019 to March 31, 2022.

  • Auction Schedule The Auction Agent shall conduct Auctions in accordance with the schedule set forth below. Such schedule may be changed by the Auction Agent with the consent of the Company, which consent shall not be withheld unreasonably. The Auction Agent shall give notice of any such change to each Broker-Dealer. Such notice shall be received prior to the first Auction Date on which any such change shall be effective. Time Event ---- ----- By 9:30 A.M. Auction Agent advises the Company and the Broker-Dealers of the Reference Rate and the Maximum Applicable Rate as set forth in Section 2.2(e)(i) hereof.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Wage Schedules The Parties shall, upon completing a wage adjustment calculation, forthwith prepare, publish, post and distribute a wage schedule resulting therefrom. The final determination of the wage schedules shall be issued no later than the 7th day of March or September, for the May and November adjustments, respectively.

  • First Schedule Liquidated Damages

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!