System Access Control Data processing systems used to provide the Cloud Service must be prevented from being used without authorization. Measures: • Multiple authorization levels are used when granting access to sensitive systems, including those storing and processing Personal Data. Authorizations are managed via defined processes according to the SAP Security Policy • All personnel access SAP’s systems with a unique identifier (user ID). • SAP has procedures in place so that requested authorization changes are implemented only in accordance with the SAP Security Policy (for example, no rights are granted without authorization). In case personnel leaves the company, their access rights are revoked. • SAP has established a password policy that prohibits the sharing of passwords, governs responses to password disclosure, and requires passwords to be changed on a regular basis and default passwords to be altered. Personalized user IDs are assigned for authentication. All passwords must fulfill defined minimum requirements and are stored in encrypted form. In the case of domain passwords, the system forces a password change every six months in compliance with the requirements for complex passwords. Each computer has a password-protected screensaver. • The company network is protected from the public network by firewalls. • SAP uses up–to-date antivirus software at access points to the company network (for e-mail accounts), as well as on all file servers and all workstations. • Security patch management is implemented to provide regular and periodic deployment of relevant security updates. Full remote access to SAP’s corporate network and critical infrastructure is protected by strong authentication.
Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.
Start-Up and Synchronization Consistent with the mutually acceptable procedures of the Developer and Connecting Transmission Owner, the Developer is responsible for the proper synchronization of the Large Generating Facility to the New York State Transmission System in accordance with NYISO and Connecting Transmission Owner procedures and requirements.
Commencement of Interconnection Activities If the Developer executes the final LGIA, the ISO, Connecting Transmission Owner and the Developer shall perform their respective obligations in accordance with the terms of the LGIA, subject to modification by FERC. Upon submission of an unexecuted LGIA in accordance with Section 30.11.3, the Parties shall promptly comply with the unexecuted LGIA, subject to modification by FERC.
Construction Phase Services 3.1.1 – Basic Construction Services
Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.
Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.
WORK ACCESS The Association shall provide a current, written list of its Association Representatives to all heads of departments, offices, or bureaus represented herein and the CAO. The Association shall be responsible for keeping the list current. An Association Representative shall have access to department, office, or bureau facilities where Unit members are employed during regular working hours to assist employees covered under this MOU in addressing grievances when such Association assistance is requested by a grievant(s) or to investigate matters arising out of the application of the provisions of this MOU. The Association Representative shall request authorization for such visits by contacting the designated Management representative of the head of the office, department, or bureau. In the event immediate access cannot be authorized, the designated Management representative shall inform the Association Representative as to the earliest time when access can be granted. This Article shall not be construed as a limitation on the power of the head of a department, office, or bureau to restrict access to areas designated for security or confidential purposes.
Local Control Center, Metering and Telemetry The NTO shall operate, pursuant to ISO Tariffs, ISO Procedures, Reliability Rules and all other applicable reliability rules, standards and criteria on a twenty-four (24) hour basis, a suitable local control center(s) with all equipment and facilities reasonably required for the ISO to exercise ISO Operational Control over NTO Transmission Facilities Under ISO Operational Control, and for the NTO to fulfill its responsibilities under this Agreement. Operation of the NYS Power System is a cooperative effort coordinated by the ISO control center in conjunction with local control centers and will require the exchange of all reasonably necessary information. The NTO shall provide the ISO with Supervisory Control and Data Acquisition (“SCADA”) information on facilities listed in Appendices A-1 and A-2 herein as well as on generation and merchant transmission resources interconnected to the NTO’s transmission facilities pursuant to the ISO OATT. The NTO shall provide metering data for its transmission facilities to the ISO, unless other parties are authorized by the appropriate regulatory authority to provide metering data. The NTO shall collect and submit to the ISO billing quality metering data and any other information for its transmission facilities required by the ISO for billing purposes. The NTO shall provide to the ISO the telemetry and other operating data from generation and merchant transmission resources interconnected to its transmission facilities that the ISO requires for the operation of the NYS Power System. The NTO will establish and maintain a strict code of conduct to prevent such information from reaching any unauthorized person or entity.
Scope of Interconnection Service 1.3.1 The NYISO will provide Energy Resource Interconnection Service to Interconnection Customer at the Point of Interconnection.