Change of Contract Price. A. The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph 10.05. B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:
Appears in 5 contracts
Samples: Inspection and Service Contract, Maintenance Contract for Electrical Work, Maintenance Contract
Change of Contract Price. A. The Contract Price may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted delivered by the party making the Claim to the ENGINEER and the other party to the Contract promptly in accordance with the provisions of paragraph 10.05Paragraph 13.03.
B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:
Appears in 1 contract
Change of Contract Price. SAMPLE
A. The Contract Price may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the ENGINEER Architect and the other party to the Contract in accordance with the provisions of paragraph Paragraph 10.05.
B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:
Appears in 1 contract
Change of Contract Price. A. The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the ENGINEER Owner’s Representative and the other party to the Contract in accordance with the provisions of paragraph 10.05.
B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:
Appears in 1 contract
Samples: Contract
Change of Contract Price. A. The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Claim claim for an adjustment in the Contract Price shall be based on made by written notice submitted by the party making the Claim claim to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph 10.05and must be approved by both parties.
B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:
Appears in 1 contract
Samples: Construction Contract