Change Order Control. CHANGE ORDERS SHALL BE MANAGED THROUGH THE OWNER’S ORACLE’S CONTRACT MANAGEMENT (FORMERLY KNOWN AS EXPEDITION) SOFTWARE. The CM shall establish and implement a change order control system. 3.5.3.3.1 All proposed Owner-initiated change orders shall first be described in detail in writing by the Owner to the CM and then shall be forwarded in a request for proposal to the Contractor, accompanied by technical drawings and specifications prepared by the Designer. In response to the request for a proposal, the Contractor shall submit to the CM for evaluation detailed information concerning the costs and time adjustments, if any, necessary to perform the proposed change order work. The CM shall review the Contractor’s proposal, shall discuss the proposed change order with the Contractor and endeavor to determine the Contractor’s basis for the cost and time to perform the Work and, as applicable, the effect, if any, on the Guaranteed Maximum Price. The CM shall present its findings to the Owner and, following Owner acceptance, THE DESIGNER shall prepare the change order documents for signature by the CM and Owner. Upon execution of the change order documents between the CM and Owner, the CM shall prepare change order documents for signature by the affected Contractor. The CM shall verify that the Work, and any adjustment of time required by approved change orders has been incorporated into the Contractor’s Construction Schedule. 3.5.3.3.2 The CM shall review the contents of all Contractor- requested changes to the contract time or price, endeavor to determine the effect, if any, on the Guaranteed Maximum Price. The CM shall provide the Designer a copy of each change request, and the CM shall, in its evaluations of the Contractor’s request, consider the Designer’s comments regarding the proposed changes. The CM shall present its findings to the Owner regarding the proposed changes and at the Owner’s direction, shall prepare the change order documents for signature by the CM and Owner. Upon execution of the change order documents between the CM and Owner, the CM shall prepare change order documents for signature by the affected Contractor.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Construction Manager (Construction Manager at Risk), Standard Form of Agreement Between Owner and Construction Manager (Construction Manager at Risk)
Change Order Control. CHANGE ORDERS SHALL BE MANAGED THROUGH THE OWNER’S ORACLE’S CONTRACT MANAGEMENT (FORMERLY KNOWN AS EXPEDITION) SOFTWARE. The CM shall establish and implement a change order control system.
3.5.3.3.1 25.4.1. All proposed Owner-initiated change orders shall first be described in detail in writing by the Owner Owner, or the Designer if so requested by the Owner, and forwarded to the CM. The CM and shall then shall be forwarded in forward a request for proposal to the Contractorappropriate Contractor (or Contractors), accompanied by technical drawings Drawings and specifications Specifications prepared by the Designer. In response to the request for a proposal, the Contractor shall submit to the CM for evaluation detailed information concerning the costs and time adjustments, if any, necessary to perform the proposed change order work. Pricing for the proposal shall be in accordance with the requirements for changes to the GMP set forth in Article 26. The CM shall thoroughly, completely and critically review the Contractor’s proposal, shall discuss the proposed change order with the Contractor and endeavor to determine the Contractor’s basis for the cost and time to perform the Work and, as applicable, the effect, if any, on the Guaranteed Maximum PriceGMP. The CM shall present its findings to the Owner andand the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal or proposals should be accepted or rejected and explaining what the CM did to substantiate the pricing by the Contractor. Following acceptance of the proposal by the Owner, following Owner acceptance, THE DESIGNER the Designer shall prepare the change order documents for signature by the CM and the Owner. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the affected ContractorContractor(s). The CM shall verify that the Work, and any adjustment of time required by approved change orders has been incorporated into the Contractor’s Construction Schedule.
3.5.3.3.2 25.4.2. The CM shall thoroughly, completely and critically review the contents of all Contractor- requested changes to the contract time or price, endeavor determine whether an adjustment to the GMP or the Master Schedule is warranted under the Agreement, and determine the effectamount or length, if any, on of the Guaranteed Maximum Priceallowable adjustment to the GMP and the Master Schedule. The If the CM believes that an adjustment to this Agreement might be warranted by a Contractor change request, the CM shall provide the Designer with a copy of each the change request, and the CM shall, in its evaluations of the Contractor’s request, consider the Designer’s comments regarding the proposed changes. The CM shall present its findings to the Owner and the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal regarding the proposed changes should be accepted or rejected and at explaining what the Owner’s directionCM did to substantiate the pricing by the Contractor. If, after review by the Owner and the Designer, the Owner determines that an adjustment to the GMP or Master Schedule is warranted, the Designer shall prepare the change order documents for signature by the CM CM, the Owner and Ownerthe Designer. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the each affected Contractor.
25.4.3. In instances where a lump sum or unit price is not authorized by the Owner in a change order prior to performing Work described in a request for proposal as provided in Section 26.1.3, the CM shall request from the Contractor records of the cost of payroll, materials and equipment and the amount of payments to subcontractors incurred by the Contractor in performing the Work. These cost records will be available to determine equitable compensation to the Contractor for the change order Work.
25.4.4. Trade-Off Studies: The CM shall provide trade-off studies for various minor construction components. The results of the trade-off studies shall be in report form and distributed to the Owner and Designer.
Appears in 1 contract
Samples: Architect Contract
Change Order Control. CHANGE ORDERS SHALL BE MANAGED THROUGH THE OWNER’S ORACLE’S CONTRACT MANAGEMENT (FORMERLY KNOWN AS EXPEDITION) SOFTWARE. The CM shall establish and implement a change order control system.
3.5.3.3.1 24.4.1. All proposed Owner-initiated change orders shall first be described in detail in writing by the Owner Owner, or the Designer if so requested by the Owner, and forwarded to the CM. The CM and shall then shall be forwarded in forward a request for proposal to the Contractorappropriate Contractor (or Contractors), accompanied by technical drawings Drawings and specifications Specifications prepared by the Designer. In response to the request for a proposal, the Contractor shall submit to the CM for evaluation detailed information concerning the costs and time adjustments, if any, necessary to perform the proposed change order work. Pricing for the proposal shall be in accordance with the requirements for changes to the Guaranteed Maximum Price set forth in Article 25. The CM shall thoroughly, completely and critically review the Contractor’s proposal, shall discuss the proposed change order with the Contractor and endeavor to determine the Contractor’s basis for the cost and time to perform the Work and, as applicable, the effect, if any, on the Guaranteed Maximum Price. The CM shall present its findings to the Owner andand the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal or proposals should be accepted or rejected and explaining what the CM did to substantiate the pricing by the Contractor. Following acceptance of the proposal by the Owner, following Owner acceptance, THE DESIGNER the Designer shall prepare the change order documents for signature by the CM and the Owner. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the affected ContractorContractor(s). The CM shall verify that the Work, and any adjustment of time required by approved change orders has been incorporated into the Contractor’s Construction Schedule.
3.5.3.3.2 24.4.2. The CM shall thoroughly, completely and critically review the contents of all Contractor- Contractor-requested changes to the contract time or price, endeavor determine whether an adjustment to the Guaranteed Maximum Price or the Master Schedule is warranted under the Agreement, and determine the effectamount or length, if any, on of the allowable adjustment to the Guaranteed Maximum PricePrice and the Master Schedule. The If the CM believes that an adjustment to this Agreement might be warranted by a Contractor change request, the CM shall provide the Designer with a copy of each the change request, and the CM shall, in its evaluations of the Contractor’s request, consider the Designer’s comments regarding the proposed changes. The CM shall present its findings to the Owner and the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal regarding the proposed changes should be accepted or rejected and at explaining what the Owner’s directionCM did to substantiate the pricing by the Contractor. If, after review by the Owner and the Designer, the Owner determines that an adjustment to the Guaranteed Maximum Price or Master Schedule is warranted, the Designer shall prepare the change order documents for signature by the CM CM, the Owner and Ownerthe Designer. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the each affected Contractor.
24.4.3. In instances where a lump sum or unit price is not authorized by the Owner in a change order prior to performing Work described in a request for proposal as provided in Section 25.1.3, the CM shall request from the Contractor records of the cost of payroll, materials and equipment and the amount of payments to subcontractors incurred by the Contractor in performing the Work. These cost records will be available to determine equitable compensation to the Contractor for the change order Work.
Appears in 1 contract
Samples: Construction Management Agreement
Change Order Control. CHANGE ORDERS SHALL BE MANAGED THROUGH THE OWNER’S ORACLE’S CONTRACT MANAGEMENT (FORMERLY KNOWN AS EXPEDITION) SOFTWARE. The CM shall establish and implement a change order control system.
3.5.3.3.1 25.4.1. All proposed Owner-initiated change orders shall first be described in detail in writing by the Owner Owner, or the Designer if so requested by the Owner, and forwarded to the CM. The CM and shall then shall be forwarded in forward a request for proposal to the Contractorappropriate Contractor (or Contractors), accompanied by technical drawings Drawings and specifications Specifications prepared by the Designer. In response to the request for a proposal, the Contractor shall submit to the CM for evaluation detailed information concerning the costs and time adjustments, if any, necessary to perform the proposed change order work. Pricing for the proposal shall be in accordance with the requirements for changes to the GMP set forth in Article 26. The CM shall thoroughly, completely and critically review the Contractor’s proposal, shall discuss the proposed change order with the Contractor and endeavor to determine the Contractor’s basis for the cost and time to perform the Work and, as applicable, the effect, if any, on the Guaranteed Maximum PriceGMP. The CM shall present its findings to the Owner andand the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal or proposals should be accepted or rejected and explaining what the CM did to substantiate the pricing by the Contractor. Following acceptance of the proposal by the Owner, following Owner acceptance, THE DESIGNER the Designer shall prepare the change order documents for signature by the CM and the Owner. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the affected ContractorContractor(s). The CM shall verify that the Work, and any adjustment of time required by approved change orders has been incorporated into the Contractor’s Construction Schedule.
3.5.3.3.2 25.4.2. The CM shall thoroughly, completely and critically review the contents of all Contractor- Contractor-requested changes to the contract time or price, endeavor determine whether an adjustment to the GMP or the School Project Schedule is warranted under the Agreement, and determine the effectamount or length, if any, on of the Guaranteed Maximum Priceallowable adjustment to the GMP and the School Project Schedule. The If the CM believes that an adjustment to this Agreement might be warranted by a Contractor change request, the CM shall provide the Designer with a copy of each the change request, and the CM shall, in its evaluations of the Contractor’s request, consider the Designer’s comments regarding the proposed changes. The CM shall present its findings to the Owner and the Designer in writing with a detailed explanation of why the CM believes the Contractor proposal regarding the proposed changes should be accepted or rejected and at explaining what the Owner’s directionCM did to substantiate the pricing by the Contractor. If, after review by the Owner and the Designer, the Owner determines that an adjustment to the GMP or School Project Schedule is warranted, the Designer shall prepare the change order documents for signature by the CM CM, the Owner and Ownerthe Designer. Upon execution of the change order documents between by the CM and the Owner, the CM shall prepare change order documents for signature by the each affected Contractor.
25.4.3. In instances where a lump sum or unit price is not authorized by the Owner in a change order prior to performing Work described in a request for proposal as provided in Section 26.1.3, the CM shall request from the Contractor records of the cost of payroll, materials and equipment and the amount of payments to subcontractors incurred by the Contractor in performing the Work. These cost records will be available to determine equitable compensation to the Contractor for the change order Work.
25.4.4. Trade-Off Studies: The CM shall provide trade-off studies for various minor construction components. The results of the trade-off studies shall be in report form and distributed to the Owner and Designer.
Appears in 1 contract
Samples: Architect Contract