Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or
Appears in 5 contracts
Samples: Construction Management Contract, Construction Management Services Agreement, Project Construction Management Contract
Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents Documents, or
Appears in 2 contracts
Samples: Construction Management Contract, Construction Management Contract
Changed Conditions. 42.1. 42.1 Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or
Appears in 1 contract
Samples: Construction Management Agreement
Changed Conditions. 42.1.
38.1 Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or
Appears in 1 contract
Samples: Construction Contract
Changed Conditions. 42.1. Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or
Appears in 1 contract
Samples: Project Design Build Contract