City’s Response. Upon receipt of a Claim pursuant to this Section, the City shall conduct a reasonable review of the Claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim will be processed and made within 60 days after the City issues its written statement. (A) If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion. (B) Within 30 days of receipt of a Claim, the City may request in writing additional documentation supporting the Claim or relating to defenses or Claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor. The City’s written response to the Claim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Short Form Construction Contract
City’s Response. Upon receipt of a Claim claim pursuant to this Section, the City shall conduct a reasonable review of the Claim claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim claim will be processed and made within 60 days after the City public entity issues its written statement.
(A) 3.10.4.1 If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claimclaim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(B) 3.10.4.2 Within 30 days of receipt of a Claimclaim, the City may request in writing additional documentation supporting the Claim claim or relating to defenses or Claims the claims City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor. The .
3.10.4.3 City’s written response to the Claimclaim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim claim is less than $50,00050,000.00, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
City’s Response. Upon receipt of a Claim claim pursuant to this Section, the City shall conduct a reasonable review of the Claim claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim claim will be processed and made within 60 days after the City public entity issues its written statement.
(A) 3.10.4.1 If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claimclaim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(B) 3.10.4.2 Within 30 days of receipt of a Claimclaim, the City may request in writing additional documentation supporting the Claim claim or relating to defenses or Claims the claims City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor. The .
3.10.4.3 City’s written response to the Claimclaim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
City’s Response. Upon receipt of a Claim claim pursuant to this Section, the City shall conduct a reasonable review of the Claim claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim claim will be processed and made within 60 days after the City issues its written statement.
(A) i. If the City needs approval from its governing body the City Council to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claimclaim, and the City’s governing body City Council does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body City Council after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(B) ii. Within 30 days of receipt of a Claimclaim, the City may request in writing additional documentation supporting the Claim claim or relating to defenses or Claims claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor.
iii. The City’s written response to the Claimclaim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.
Appears in 1 contract
Samples: Public Works Agreement
City’s Response. Upon receipt of a Claim claim pursuant to this Section, the City shall conduct a reasonable review of the Claim claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim claim will be processed and made within 60 days after the City public entity issues its written statement.
(A1) If the City needs approval from its governing body the City Council to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claimclaim, and the City’s governing body City Council does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body City Council after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(B2) Within 30 days of receipt of a Claimclaim, the City may request in writing additional documentation supporting the Claim claim or relating to defenses or Claims claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor. .
(3) The City’s written response to the Claimclaim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.
Appears in 1 contract
Samples: Audio Video Installation Contract
City’s Response. Upon receipt of a Claim claim pursuant to this Sectionsection, the City shall conduct a reasonable review of the Claim claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim claim will be processed and made within 60 days after the City issues its written statement.
(Ai) If the City needs approval from its governing body the City Council to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claimclaim, and the City’s governing body City Council does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three (3) days following the next duly publicly noticed meeting of the City’s governing body City Council after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(Bii) Within 30 days of receipt of a Claimclaim, the City may request in writing additional documentation supporting the Claim claim or relating to defenses or Claims claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the Contractor. .
(iii) The City’s written response to the Claimclaim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.