Common use of Claims by Contractor Clause in Contracts

Claims by Contractor. 1. Claims by Contractor against City are subject to the terms and conditions of this Article 15, and strict compliance herewith shall be a condition precedent to any liability of City therefore. 2. All claims for additional compensation or additional time, regardless of their nature, when they occur, or whether they occur during the design or construction phase, shall be governed by the City of Buckeye Procurement Code. 3. Contractor shall provide, and continue to provide, to City all such documentation, including cost and time records, as and when City may request so that City may evaluate Contractor's claim. 4. Contractor shall continue its performance under this Contract regardless of the existence of any claims submitted by Contractor against City. 5. In the event Contractor seeks to make a claim for an increase in the Construction Price, as a condition precedent to any liability of City for any claim, Contractor shall strictly comply with the requirements of Paragraph 2 above and such notice shall be given by Contractor before proceeding to execute any alleged additional or changed Construction Work. Failure of the condition precedent to occur shall constitute a waiver by Contractor of any claim. 6. In connection with any claim by Contractor against City for compensation in excess of the Construction Price, any liability of City shall be strictly limited to the Cost of the Construction Work and Design Services if required as defined and allowed in this Contract and subsequent Delivery Orders and shall in no event include, indirect, consequential, impact or other costs, expenses or damages of Contractor or its Subcontractors. City shall not be liable to Contractor for claims of third parties, including Subcontractors, for acts, omissions, events, or conditions for which City would not be liable to Contractor under the terms of the Contract. As a condition precedent to City's liability to Contractor for any loss or damage resulting from claims of third parties, including Subcontractors, such third parties must have complied with all conditions contained in their agreements with Contractor and such claims must have been submitted to City by Contractor in strict compliance with all the requirements of this Article. City shall not be liable to Contractor for claims of third parties including Subcontractors, unless and until the liability of Contractor has been established in a court of competent jurisdiction. 7. The resolution of any claim under this Article shall be reflected by a Change Order or Supplemental Agreement executed by City and Contractor.

Appears in 3 contracts

Samples: Job Order Contract, Job Order Contract, Job Order Contract

AutoNDA by SimpleDocs

Claims by Contractor. 1. Claims by Contractor against City are subject to the terms and conditions of this Article 15, and strict compliance herewith shall be a condition precedent to any liability of City therefore. 2. All claims for additional compensation or additional time, regardless of their nature, when they occur, or whether they occur during the design or construction phase, shall be governed by the City of Buckeye Procurement Code. 3. Contractor shall provide, and continue to provide, to City all such documentation, including cost and time records, as and when City may request so that City may evaluate Contractor's claim. 4. Contractor shall continue its performance under this Contract regardless of the existence of any claims submitted by Contractor against City. 5. In the event Contractor seeks to make a claim for an increase in the Construction Price, as a condition precedent to any liability of City for any claim, Contractor shall strictly comply with the requirements of Paragraph 2 above and such notice shall be given by Contractor before proceeding to execute any alleged additional or changed Construction Work. Failure of the condition precedent to occur shall constitute a waiver by Contractor of any claim. 6. In connection with any claim by Contractor against City for compensation in excess of the Construction Price, any liability of City shall be strictly limited to the Cost of the Construction Work and Design Services if required as defined and allowed in this Contract and subsequent Delivery Job Orders and shall in no event include, indirect, consequential, impact or other costs, expenses or damages of Contractor or its Subcontractors. City shall not be liable to Contractor for claims of third parties, including Subcontractors, for acts, omissions, events, or conditions for which City would not be liable to Contractor under the terms of the Contract. As a condition precedent to City's liability to Contractor for any loss or damage resulting from claims of third parties, including Subcontractors, such third parties must have complied with all conditions contained in their agreements with Contractor and such claims must have been submitted to City by Contractor in strict compliance with all the requirements of this Article. City shall not be liable to Contractor for claims of third parties including Subcontractors, unless and until the liability of Contractor has been established in a court of competent jurisdiction. 7. The resolution of any claim under this Article shall be reflected by a Change Order or Supplemental Agreement executed by City and Contractor.

Appears in 2 contracts

Samples: Job Order Contract for Road Construction Services, Job Order Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!