Common use of COMPLETION AND HANDOVER INSPECTION Clause in Contracts

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 4 contracts

Samples: Building Agreement, Building Agreement, Building Agreement

AutoNDA by SimpleDocs

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSPrincipal Agent. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may havehave up to the Completion Date. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 4 contracts

Samples: Building Agreement, Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Over Inspection at any pre-pre- arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSArchitect or the Principal Agent. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause Clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 All undertakings and commitments given by the Developer and/or the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 3 contracts

Samples: Building Agreement, Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection within 5 (Five) Business Days after having been requested to do so at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. The Employer will sign the Defect List and all documents necessary to effect payments. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 3 contracts

Samples: Building Agreement, Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection within 5 (Five) Business Days after having been requested to do so at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. The Employer will sign the Defect List and all documents necessary to effect payments prior to the handing-over of the keys of the Works. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSArchitect. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 2 contracts

Samples: Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSPrincipal Agent in terms of the JBCC. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause Clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 2 contracts

Samples: Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSArchitect. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 The Employer will ensure that he is satisfied with the building works and will sign the “Happy Letter” before the house keys are handed to the Employer and before occupation is taken. 8.6 All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 2 contracts

Samples: Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 The Employer will ensure that he is satisfied with the building works and will sign the “Happy Letter” before the house keys are handed to the Employer and before occupation is taken. 8.6 All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 2 contracts

Samples: Building Agreement, Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. ‌ 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Over Inspection at any pre-pre- arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSArchitect or the Principal Agent. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause Clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 All undertakings and commitments given by the Developer and/or the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 1 contract

Samples: Building Agreement

AutoNDA by SimpleDocs

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto. 8.6 The Purchaser will sign the Happy Letter and/or Letter of Completion prior to receiving the keys to the property and taking occupation.

Appears in 1 contract

Samples: Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. 8.1 The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. 8.2 If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QSprincipal agent in terms of the JBCC. 8.3. 8.3 The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. 8.4 Notwithstanding the provisions of this clause Clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. 8.5 All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 1 contract

Samples: Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. a. The Parties or their representatives shall be obliged to attend the Hand-over Handover Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. b. If the Employer fails to attend a Hand-over Handover Inspection within a reasonable period after having received written notice thereof by from the Contractor, then the Completion Date will be determined by the QSappointed Principal Agent. 8.3. c. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. d. Notwithstanding the provisions of this clause 8Clause 7, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. e. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 1 contract

Samples: Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer.. INITIAL 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 1 contract

Samples: Building Agreement

COMPLETION AND HANDOVER INSPECTION. 8.1. The Parties or their representatives shall be obliged to attend the Hand-over Inspection at any pre-arranged time, during which inspection the Parties shall agree to the Defects List. 8.2. If the Employer fails to attend a Hand-over Inspection within a reasonable period after having received written notice thereof by the Contractor, then the Completion Date will be determined by the QS. 8.3. The Contractor shall remedy the defects on the Defects List as soon as reasonably possible. 8.4. Notwithstanding the provisions of this clause 8, the Contractor shall strictly enforce, for the benefit of the Employer, any guarantee or warranty which it may have. In as far as such guarantee or warranty relates to the Works, the Contractor hereby cedes all its rights in terms thereof to the Employer. 8.5. All undertakings and commitments given by the Contractor to the Employer in terms of this Agreement are personal to the Employer who shall not be entitled to cede, assign or make over its rights thereto.

Appears in 1 contract

Samples: Building Agreement