Completion of Work. Contractor is accountable for completing the Work within the Contract Time stated in the Contract, or as otherwise amended by Change Order. 8.4.1 If, in the judgment of Owner, the work is behind schedule and the rate of placement of Work is inadequate to regain scheduled progress to ensure timely completion of the entire Work or a separable portion thereof, Contractor, when so informed by Owner, shall immediately take action to increase the rate of work placement by: .1 An increase in working forces. .2 An increase in equipment or tools. .3 An increase in hours of work or number of shifts. .4 Expedite delivery of materials. .5 Other action proposed, if acceptable to Owner. 8.4.2 Within ten (10) calendar days after such notice from Owner, Contractor shall notify Owner in writing of the specific measures taken or planned to increase the rate of progress. Contactor shall include an estimate as to the date of scheduled progress recovery and an updated Work Progress Schedule illustrating Contractor’s plan for achieving timely completion of the Project. Should Owner deem the plan of action inadequate, Contractor shall take additional steps or make adjustments, as necessary, to its plan of action until it meets with Owner’s approval.
Appears in 25 contracts
Samples: Contract for Construction, Contract for Construction, Construction Contract
Completion of Work. Contractor is accountable for completing the Work within the Contract Time stated in the Contract, or as otherwise amended by Change Order.
8.4.1 If, in the judgment of Owner, the work is behind schedule and the rate of placement of Work is inadequate to regain scheduled progress to ensure timely completion of the entire Work or a separable portion thereof, Contractor, when so informed by Owner, shall immediately take action to increase the rate of work placement by:
.1 An increase in working forces.
.2 An increase in equipment or tools.
.3 An increase in hours of work or number of shifts.
.4 Expedite delivery of materials. .
.5 Other action proposed, if acceptable to Owner.
8.4.2 Within ten (10) calendar days after such notice from Owner, Contractor shall notify Owner in writing of the specific measures taken or planned to increase the rate of progress. Contactor shall include an estimate as to the date of scheduled progress recovery and an updated Work Progress Schedule illustrating Contractor’s plan for achieving timely completion of the Project. Should Owner deem the plan of action inadequate, Contractor shall take additional steps or make adjustments, as necessary, to its plan of action until it meets with Owner’s approval.
Appears in 4 contracts
Samples: Construction Manager at Risk Contract, Construction Manager at Risk Contract, Construction Manager at Risk Contract