Connectivity for Evacuation. 6.1.1 Connectivity for evacuation will be at the bus bar level of the 11 kV/22 kV/ 33 kV and EHV voltage level of MSEDCL / STU substations. The SPV shall abide by the relevant CERC/ MERC/CEA regulations and Grid Code (as amended and revised from time to time), for interconnection with grid. 6.1.2 The connectivity clearances required for establishment of the Units and the Project in its entirety shall be through a single window portal of the Maharashtra Energy Development Agency that will be accessible to the SPV.
Appears in 16 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Connectivity for Evacuation. 6.1.1 Connectivity for evacuation will be at the bus bar level of the 11 kV/22 kV/ 33 kV and EHV voltage level of MSEDCL / STU substations. The SPV shall abide by the relevant CERC/ MERC/CEA regulations and Grid Code (as amended and revised from time to time), for interconnection with grid.
6.1.2 The connectivity clearances required for establishment of the Units and the Project in its entirety shall be through a single window portal of the Maharashtra Energy Development Agency that will be accessible to the SPV.
Appears in 1 contract
Samples: Power Purchase Agreement