Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the Engineer's instructions under sub-clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to sub-clause 20.1 [Contractor's Claims] to: (a) an extension of time for any such delay, if completion is or will be delayed, under sub-clause 8.4 [Extension of Time for Completion]; and (b) payment of any such Cost, which shall be added to the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with sub-clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's faulty design, workmanship or materials, or of the Contractor's failure to protect, store or secure in accordance with sub-clause 8.8 [Suspension of Work].
Appears in 9 contracts
Samples: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract
Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the Engineer's instructions under sub-clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to sub-clause
clause 20.1 [Contractor's Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under sub-clause 8.4 [Extension of Time for Completion]; and
(b) payment of any such Cost, which shall be added to the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with sub-clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's faulty design, workmanship or materials, or of the Contractor's failure to protect, store or secure in accordance with sub-sub- clause 8.8 [Suspension of Work].
Appears in 4 contracts
Samples: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract
Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the Engineer's ’s instructions under subSub-clause Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to subSub-clause
Clause 20.1 [Contractor's ’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under subSub-clause Clause 8.4 [Extension of Time for Completion]; , and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with subSub-clause Clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's ’s faulty design, workmanship or materials, or of the Contractor's ’s failure to protect, store or secure in accordance with subSub-clause Clause 8.8 [Suspension of Work].
Appears in 2 contracts
Samples: Construction Contract, Contract Agreement
Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the EngineerContract Awarder's instructions under subSub-clause Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer Contract Awarder and shall be entitled subject to subSub-clause
Clause 20.1 [Contractor's Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under sub-clause SubClause 8.4 [Extension of Time for Completion]; , and
(b) payment of any such Cost, which shall be added to the Contract Price. After receiving this notice, the Engineer Contract Awarder shall proceed in accordance with subSub-clause Clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's faulty designISBL Design, workmanship or materials, or of the Contractor's failure to protect, store or secure in accordance with subSub-clause Clause 8.8 [Suspension of Work].
Appears in 2 contracts
Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)
Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the Engineer's ’s instructions under subSub-clause Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to subSub-clause
Clause 20.1 [Contractor's ’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under sub-clause Sub- Clause 8.4 [Extension of Time for Completion]; , and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with subSub-clause Clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's ’s faulty design, workmanship or materials, or of the Contractor's ’s failure to protect, store or secure in accordance with sub-clause Sub- Clause 8.8 [Suspension of Work].
Appears in 1 contract
Samples: Unit Price Contract
Consequences of Suspension. If the Contractor suffers delay and/or incurs Cost from complying with the Engineer's ’s instructions under subSub-clause Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to subSub-clause
Clause 20.1 [Contractor's ’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under subSub-clause Clause 8.4 [Extension of Time for Completion]; , and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with sub-clause Sub- Clause 3.5 [Determinations] to agree or determine these matters. The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor's ’s faulty design, workmanship or materials, or of the Contractor's ’s failure to protect, store or secure in accordance with subSub-clause Clause 8.8 [Suspension of Work].
Appears in 1 contract
Samples: Unit Price Contract