Construction initiation. Within [•] Days of the Effective Date, the Concessionaire shall before the actual construction of the Works shall: (a) submit to FBR and Independent Engineer: (i) the Schedule Y [Project Implementation Programme]; (ii) the Schedule O [Project Completion Schedule]; (iii) its construction methodology; and (iv) its quality assurance procedures. (b) appoint its representative duly authorized to deal with FBR in respect of all matters under or arising out of or relating to this Agreement; (c) undertake, do and perform all such acts, deeds and things as may be necessary or required before commencement of construction under and in accordance with this Agreement and the Applicable Laws; and (d) make its own arrangements for quarrying of materials needed for the Project under and in accordance with the Applicable Laws.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Construction initiation. Within [•] Days of the Effective Date, the Concessionaire shall before the actual construction of the Works shall:
(a) submit to FBR and Independent Engineer:
(i) the Schedule Y [Project Implementation Programme];
(ii) the Schedule O [Project Completion Schedule];
(iii) its construction methodology; and
(iv) its quality assurance procedures.
(b) appoint its representative duly authorized to deal with FBR in respect of all matters under or arising out of or relating to this Agreement;
(c) undertake, do and perform all such acts, deeds and things as may be necessary or required before commencement of construction under and in accordance with this Agreement and the Applicable Laws; and
(d) make its own arrangements for quarrying of materials needed for the Project under and in accordance with the Applicable Laws.
Appears in 1 contract
Samples: Concession Agreement