Contents of Time Extension Requests. Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
Appears in 64 contracts
Samples: Contract for Construction, Contract for Construction, Contract for Construction
Contents of Time Extension Requests. The Contractor shall provide with each Time Extension Request time extension request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
Appears in 41 contracts
Contents of Time Extension Requests. The Contractor shall provide with each Time Extension Request time extension request a quantitative demonstration of the impact of the delay on project Project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
Appears in 7 contracts
Samples: assets.system.tamus.edu, assets.system.tamus.edu, assets.system.tamus.edu
Contents of Time Extension Requests. Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
.1 The nature of the delay and its cause; the basis of Contractor’s claim of entitlement to a time extension. .2 Documentation of the actual impacts of the claimed delay on the critical path indicated in Contractor’s Work Progress Schedule, and any concurrent delays.
Appears in 1 contract
Samples: agenda.wilcotx.gov