Contents of Time Extension Requests. The Contractor shall provide with each time extension request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth: 9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension. 9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays. 9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 41 contracts
Samples: Design Build Contract, Construction Management Agreement, Construction Management Agreement
Contents of Time Extension Requests. The Contractor shall provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 34 contracts
Samples: General Construction Services Contract, General Construction Services Contract, Construction Manager at Risk Contract
Contents of Time Extension Requests. The Contractor shall provide with each time extension request a quantitative demonstration of the impact of the delay on project Project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 10 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Contract
Contents of Time Extension Requests. The Contractor shall provide Provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project Project completion time, based on the Work Progress Schedule. The Contractor shall include Include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 1 contract
Samples: Contract
Contents of Time Extension Requests. The Contractor shall provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 8.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 8.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delaysconcurrentdelays.
9.9.3.3 8.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 1 contract
Samples: Standard Agreement