Common use of Contents of Time Extension Requests Clause in Contracts

Contents of Time Extension Requests. Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth: .1 The nature of the delay and its cause; the basis of Contractor’s claim of entitlement to a time extension. .2 Documentation of the actual impacts of the claimed delay on the critical path indicated in Contractor’s Work Progress Schedule, and any concurrent delays.

Appears in 23 contracts

Samples: Construction Contract, Contract for Construction, Contract for Construction

AutoNDA by SimpleDocs

Contents of Time Extension Requests. Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth: .1 8.9.3.1 The nature of the delay and its cause; the basis of Contractor’s claim of entitlement to a time extension. .2 . 8.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in Contractor’s Work Progress Schedule, and any concurrent delays.critical

Appears in 1 contract

Samples: Design Build Services Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!