Common use of Contract Price Adjustments Clause in Contracts

Contract Price Adjustments. 9.4.1 The increase or decrease in Contract Price resulting from a change in the Work shall be determined by one or more of the following methods: .1 Unit prices set forth in the Agreement or as subsequently agreed to between the parties; .2 A mutually accepted, lump sum, properly itemized and supported by sufficient substantiating data to permit evaluation by Owner; .3 Costs, fees and any other markups set forth in the Agreement; and .4 If an increase or decrease cannot be agreed to as set forth in items .1 through .3 above and Owner issues a Work Change Directive, the cost of the change of the Work shall be determined by the reasonable expense and savings in the performance of the Work resulting from the change, including a reasonable overhead and profit, as may be set forth in the Agreement. If the net result of both additions and deletions to the Work is an increase in the Contract Price, overhead and profit shall be calculated on the basis of the net increase to the Contract Price. If the net result of both additions and deletions to the Work is a decrease in the Contract Price, there shall be no overhead or profit adjustment to the Contract Price. Design-Builder shall maintain a documented, itemized accounting evidencing the expenses and savings associated with such changes. 9.4.2 If unit prices are set forth in the Contract Documents or are subsequently agreed to by the parties, but application of such unit prices will cause substantial inequity to Owner or Design-Builder because of differences in the character or quantity of such unit items as originally contemplated, such unit prices shall be equitably adjusted. 9.4.3 If Owner and Design-Builder disagree upon whether Design-Builder is entitled to be paid for any services required by Owner, or if there are any other disagreements over the scope of Work or proposed changes to the Work, Owner and Design-Builder shall resolve the disagreement pursuant to Article 10 hereof. As part of the negotiation process, Design-Builder shall furnish Owner with a good faith estimate of the costs to perform the disputed services in accordance with Owner's interpretations. If the parties are unable to agree and Owner expects Design-Builder to perform the services in accordance with Owner's interpretations, Design-Builder shall proceed to perform the disputed services, conditioned upon Owner issuing a written order to Design-Builder (i) directing Design-Builder to proceed and (ii) specifying Owner's interpretation of the services that are to be performed. If this occurs, Design-Builder shall be entitled to submit in its Applications for Payment an amount equal to fifty percent (50%) of its reasonable estimated direct cost to perform the services, and Owner agrees to pay such amounts, with the express understanding that (i) such payment by Owner does not prejudice Owner's right to argue that it has no responsibility to pay for such services and (ii) receipt of such payment by Design-Builder does not prejudice Design-Builder's right to seek full payment of the disputed services if Owner's order is deemed to be a change to the Work.

Appears in 3 contracts

Samples: Standard Form of Agreement Between Owner and Design Builder—lump Sum (Aventine Renewable Energy Holdings Inc), Standard Form of Agreement Between Owner and Design Builder—lump Sum (Aventine Renewable Energy Holdings Inc), Standard Form of Agreement Between Owner and Design Builder Lump Sum (Husker Ag Processing LLC)

AutoNDA by SimpleDocs

Contract Price Adjustments. 9.4.1 7.4.1 The increase or decrease in Contract Price resulting from a change in the Work shall be determined by one or more of the following methods: .1 1. Unit prices set forth in the Agreement or as subsequently agreed to between the partiesparties (which may include daily or monthly overhead rates for the extension of services); .2 2. A mutually accepted, mutually-accepted lump sum, properly itemized and supported by sufficient substantiating data to permit evaluation by Owner; .3 3. Costs, fees and any other markups set forth in the Agreement; and .4 4. If an increase or decrease cannot be agreed to as set forth in items .1 1 through .3 3 above and Owner issues a Work Change Directive, the cost of the change of the Work shall be determined by the reasonable expense and savings in the performance of the Work resulting from the change, including a reasonable overhead and profit, as may be set forth in the Agreement. If the net result of both additions and deletions to the Work is an increase or a decrease in the Contract Price, overhead and profit shall be calculated on the basis of the net increase to the Contract Price. If the net result of both additions and deletions to the Work is a or decrease in the Contract Price, there shall be no overhead or profit adjustment to the Contract Price. Design-Builder shall maintain a documented, itemized accounting evidencing the expenses and savings associated with such changes. 9.4.2 7.4.2 If unit prices are set forth in the Contract Documents or are subsequently agreed to by the parties, but application of such unit prices will cause substantial inequity to Owner or Design-Builder because of differences in the character or quantity of such unit items as originally contemplated, such unit prices shall be equitably adjusted. 9.4.3 7.4.3 If Owner and Design-Design Builder disagree upon whether Design-Builder is entitled to be paid for any services required by Owner, or if there are any other disagreements over the scope of Work or proposed changes to the Work, Owner and Design-Builder shall resolve the disagreement pursuant to Article 10 hereofGC 8.0. As part of the negotiation process, Design-Builder shall furnish Owner with a good faith estimate of the costs to perform the disputed services in accordance with Owner's ’s interpretations. If the parties are unable to agree and Owner expects Design-Builder to perform the services in accordance with Owner's ’s interpretations, Design-Builder shall proceed to perform the disputed services, conditioned upon Owner issuing a written order to Design-Builder (i) directing Design-Builder to proceed and (ii) specifying Owner's ’s interpretation of the services that are to be performed. If this occursAdditional compensation, Design-Builder if any, shall be entitled resolved pursuant to submit in its Applications for Payment an amount equal to fifty percent (50%) of its reasonable estimated direct cost to perform the services, and Owner agrees to pay such amounts, with the express understanding that (i) such payment by Owner does not prejudice Owner's right to argue that it has no responsibility to pay for such services and (ii) receipt of such payment by Design-Builder does not prejudice Design-Builder's right to seek full payment of the disputed services if Owner's order is deemed to be a change to the WorkGC 8.0.

Appears in 1 contract

Samples: Design Build Agreement

Contract Price Adjustments. 9.4.1 The increase or decrease in Contract Price resulting from a change in the Work shall be determined by one or more of the following methods: .1 9.4.1.1 Unit prices set forth in the Agreement or as subsequently agreed to between the parties; .2 9.4.1.2 A mutually accepted, accepted lump sum, properly itemized and supported by sufficient substantiating data to permit evaluation by Owner; .3 9.4.1.3 Costs, fees and any other markups set forth in the Agreement; andor .4 9.4.1.4 If an increase or decrease cannot be agreed to as set forth in items .1 9.4.1.1 through .3 9.4.1.3 above and Owner issues a Work Change Directive, the cost of the change of the Work shall be determined by the reasonable expense and savings in the performance of the Work resulting from the change, including a reasonable overhead and profit, as may be set forth in the Agreement. If the net result of both additions and deletions to the Work is an increase in the Contract Price, overhead and profit shall be calculated on the basis of the net increase to the Contract Price. If the net result of both additions and deletions to the Work is a decrease in the Contract Price, there shall be no overhead or profit adjustment to the Contract Price. Design-Builder shall maintain a documented, itemized accounting evidencing the expenses and savings associated with such changes. 9.4.2 If unit prices are set forth in the Contract Documents or are subsequently agreed to by the parties, but application of such unit prices will cause substantial inequity to Owner or Design-Design- Builder because of differences in the character or quantity of such unit items as originally contemplated, such unit prices shall be equitably adjusted. 9.4.3 If Owner and Design-Builder disagree upon whether Design-Builder is entitled to be paid for any services required by Owner, or if there are any other disagreements over the scope of Work or proposed changes to the Work, Owner and Design-Builder shall resolve the disagreement pursuant to Article 10 hereof. As part of the negotiation process, Design-Builder shall furnish Owner with a good faith estimate of the costs to perform the disputed services in accordance with Owner's interpretations. If the parties are unable to agree and Owner expects Design-Builder to perform the services in accordance with Owner's interpretations, Design-Design- Builder shall proceed to perform the disputed services, conditioned upon Owner issuing a written order to Design-Builder (i) directing Design-Builder to proceed and (ii) specifying Owner's interpretation of the services that are to be performed. If this occurs, Design-Builder shall be entitled to submit in its Applications for Payment an amount equal to fifty percent (50%) of its reasonable estimated direct cost to perform the services, and Owner agrees to pay such amounts, with the express understanding that (i) such payment by Owner does not prejudice Owner's right to argue that it has no responsibility to pay for such services and (ii) receipt of such payment by Design-Builder does not prejudice Design-Builder's right to seek full payment of the disputed services if Owner's order is deemed to be a change to the Work.

Appears in 1 contract

Samples: Design Build Contract

Contract Price Adjustments. 9.4.1 13.2.1. The increase or decrease in Contract Price resulting from a change in the Work shall be determined by one or more of the following methods: .1 Unit prices set forth in the Agreement or as subsequently agreed to between the parties; .2 A a mutually accepted, accepted lump sum, properly itemized and supported by sufficient substantiating data to permit evaluation by Owner; .3 Costs, fees and any other markups set forth in the Agreement; and .4 If an increase or decrease cannot be agreed to as set forth in items .1 through .3 above and Owner issues a Work Change Directive, the cost of the change of the Work shall be determined by the reasonable expense and savings in the performance of the Work resulting from the change, including a reasonable overhead and profit, as may be set forth in the Agreement. If the net result of both additions and deletions to the Work is an increase in the Contract Price, overhead and profit shall be calculated on the basis of the net increase to the Contract Price. If the net result of both additions and deletions to the Work is a decrease in the Contract Price, there shall be no overhead or profit adjustment to the Contract Price. Design-Builder shall maintain a documented, itemized accounting evidencing the expenses and savings associated with such changes. 9.4.2 If unit prices are set forth in the Contract Documents or are subsequently agreed to by the parties, but application of such unit prices will cause substantial inequity to Owner or Design-Builder because of differences in the character or quantity of such unit items as originally contemplated, such unit prices shall be equitably adjusted. 9.4.3 13.2.2. If Owner and Design-Builder disagree upon whether Design-Builder is entitled to be paid for any services required by Owner, or if there are any other disagreements over the scope of Work or proposed changes to the Work, Owner and Design-Builder shall resolve the disagreement pursuant to Article 10 19 hereof. As part of the negotiation process, Design-Builder shall furnish Owner with a good faith estimate of the costs to perform the disputed services in accordance with Owner's ’s interpretations. If the parties are unable to agree and Owner expects Design-Builder to perform the services in accordance with Owner's ’s interpretations, Design-Builder shall proceed to perform the disputed services, conditioned upon Val-E Ethanol, LLC Fxxxx, Inc. Final January 6, 2006 Owner issuing a written order to Design-Builder (i) directing Design-Builder to proceed proceed, and (ii) specifying Owner's ’s interpretation of the services that are to be performed. If this occurs, Design-Builder shall be entitled to submit in its Applications for Payment an amount equal to fifty percent (50%) of its reasonable estimated direct cost to perform the services, and Owner agrees to pay such amounts, with the express understanding that (ix) such payment by Owner does not prejudice Owner's ’s right to argue that it has no responsibility to pay for such services services, and (iiy) receipt of such payment by Design-Builder does not prejudice Design-Builder's ’s right to seek full payment of the disputed services if Owner's ’s order is deemed to be a change to the Work.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (US BioEnergy CORP)

AutoNDA by SimpleDocs

Contract Price Adjustments. 9.4.1 13.2.1 The increase or decrease in Contract Price resulting from a change in the Work shall be determined by one or more of the following methods: .1 Unit prices set forth in the Agreement or as subsequently agreed to between the parties; .2 A a mutually accepted, accepted lump sum, properly itemized and supported by sufficient substantiating data to permit evaluation by Owner; .3 Costs, fees and any other markups set forth in the Agreement; and .4 If an increase or decrease cannot be agreed to as set forth in items .1 through .3 above and Owner issues a Work Change Directive, the cost of the change of the Work shall be determined by the reasonable expense and savings in the performance of the Work resulting from the change, including a reasonable overhead and profit, as may be set forth in the Agreement. If the net result of both additions and deletions to the Work is an increase in the Contract Price, overhead and profit shall be calculated on the basis of the net increase to the Contract Price. If the net result of both additions and deletions to the Work is a decrease in the Contract Price, there shall be no overhead or profit adjustment to the Contract Price. Design-Builder shall maintain a documented, itemized accounting evidencing the expenses and savings associated with such changes. 9.4.2 If unit prices are set forth in the Contract Documents or are subsequently agreed to by the parties, but application of such unit prices will cause substantial inequity to Owner or Design-Builder because of differences in the character or quantity of such unit items as originally contemplated, such unit prices shall be equitably adjusted. 9.4.3 13.2.2 If Owner and Design-Builder disagree upon whether Design-Builder is entitled to be paid for any services required by Owner, or if there are any other disagreements over the scope of Work or proposed changes to the Work, Owner and Design-Builder shall E ENERGY AXXXX, LLC August 1, 2006 resolve the disagreement pursuant to Article 10 19 hereof. As part of the negotiation process, Design-Builder shall furnish Owner with a good faith estimate of the costs to perform the disputed services in accordance with Owner's ’s interpretations. If the parties Parties are unable to agree and Owner expects Design-Builder to perform the services in accordance with Owner's ’s interpretations, Design-Builder shall proceed to perform the disputed services, conditioned upon Owner issuing a written order to Design-Builder (i) directing Design-Builder to proceed proceed, and (ii) specifying Owner's ’s interpretation of the services that are to be performed. If this occurs, Design-Builder shall be entitled to submit in its Applications for Payment an amount equal to fifty percent (50%) of its reasonable estimated direct cost to perform the services, and Owner agrees to pay such amounts, with the express understanding that (ix) such payment by Owner does not prejudice Owner's ’s right to argue that it has no responsibility to pay for such services services, and (iiy) receipt of such payment by Design-Builder does not prejudice Design-Builder's ’s right to seek full payment of the disputed services if Owner's ’s order is deemed to be a change to the Work.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (E Energy Adams LLC)