GMP Payment Request Sample Clauses

GMP Payment Request. 7.1.1. CM@Risk understands and agrees that at the pre-construction conference provided in Section 2.4 hereof, CM@Risk shall submit for City, RPR and Design Professional review and approval a Schedule of Values. The Schedule of Values will serve as the basis for monthly progress payments made to CM@Risk throughout the Work. 7.1.2. CM@Risk understands and agrees that at least five (5) working days prior to the date established for a Payment Request, CM@Risk shall submit an updated Project Schedule and meet with the RPR to review the progress of the Work as reflected on the Payment Request. 7.1.3. CM@Risk understands and agrees that the Payment Request shall constitute CM@Risk’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Payment Request, and that all Work shall pass to City free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project and payment, therefore. 7.1.4. CM@Risk understands and agrees that the Payment Request may request payment for stored equipment and materials, so long as CM@Risk provides evidence of said storage to City’s satisfaction, if construction progress is in reasonable conformance with the approved Project Schedule. 7.1.5. CM@Risk understands and agrees that for equipment and materials suitably stored at the Site, the equipment and materials shall be protected by insurance in accordance with the insurance requirements set out in Article 10 hereof, and City shall receive the equipment and materials free and clear of all liens and encumbrances upon payment, therefore. CM@Risk shall comply with City’s requirements herein and all Legal Requirements on storing and protecting material on Site. 7.1.6. CM@Risk understands and agrees that for materials and equipment stored off the Site and included in the Payment Request, City shall approve the storage in writing upon submission to City of evidence satisfactory to City of said storage. The material and equipment shall be stored within Bastrop County and shall be reasonably accessible for City’s inspection. CM@Risk further understands and agrees that it must protect the City's interest and shall include applicable insurance, bonding, storage, and transportation to the Site. CM@Risk shall comply with City’s requirements herein and all Legal Requirements on storing and protecting material off Site. 7.1.7. CM@Risk understands and agrees that in add...
AutoNDA by SimpleDocs
GMP Payment Request. 7.1.1 At the pre-construction conference prescribed in Section 2.4, XXXX shall submit for City’s review and approval a Schedule of Values. The Schedule of Values shall serve as the basis for monthly progress payments made to XXXX throughout the Work. 7.1.2 At least five (5) working days prior to the date established for a Payment Request, XXXX shall submit an updated Project Master Schedule and meet with the City’s Representative to review the progress of the Work as it shall be reflected on the Payment Request. 7.1.3 The Payment Request shall constitute XXXX’x representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Payment Request, and that title to all Work shall pass to City free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project. 7.1.4 The Payment Request may request payment for stored equipment and materials if construction progress is in reasonable conformance with the approved schedule. 7.1.4.1 For equipment and materials suitably stored at the Site, the equipment and materials shall be protected by suitable insurance and City shall receive the equipment and materials free and clear of all liens and encumbrances. 7.1.4.2 For materials and equipment stored off the Site, the City must approve the storage. The material and equipment must be stored within Coconino County or other Sites as may be approved and be accessible for City’s inspection. XXXX must establish City title to such materials and equipment or otherwise protect the City's interest and shall include applicable insurance, bonding, storage and transportation to the Site. 7.1.4.3 All bonds and insurance required for stored materials shall name the City as the loss payee to the extent of its interest in the stored materials. 7.1.5 XXXX shall submit to City on a monthly basis either on the first of the month for payment on the 15th or on the 19th of the month for payment on the 30th or 31st. If the payment date is on
GMP Payment Request. 7.1.1 At the pre-construction conference prescribed in Section 2.4, XXXX shall submit for City’s review and approval a Schedule of Values. The Schedule of Values shall serve as the basis for monthly progress payments made to XXXX throughout the Work. 7.1.2 At least five (5) working days prior to the date established for a Payment Request, XXXX shall submit an updated Project Master Schedule and meet with the City’s Representative to review the progress of the Work as it shall be reflected on the Payment Request. 7.1.3 The Payment Request shall constitute XXXX’x representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Payment Request, and that title to all Work shall pass to City free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project. 1. Monthly Executive summary detailing work completed during the pay period, a statement addressing the project budget and schedule and the items of work anticipated for the upcoming pay period 2. Current critical path schedule 3. Pay application cover sheet, detailed schedule of values and conditional lien waivers upon release of progress payment 4. Subcontractor and Supplier invoices and conditional lien waivers for current pay period 5. General Conditions invoices for current pay period

Related to GMP Payment Request

  • Payment Request The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

  • Stop Payment Request You may ask the Credit Union to stop payment on any check drawn upon or ACH debit scheduled from your checking account. You may request a stop payment by telephone, by mail, or in person. For checks, the stop payment will be effective if the Credit Union receives the order in time for the Credit Union to act upon the order. For ACH debits, the stop payment order must be received at least three (3) banking days before the scheduled date of the transfer. You must state the number of the account, date, and the exact amount of the check or item and the number of the check or originator of the ACH debit. If you give the Credit Union incorrect or incomplete information, the Credit Union will not be responsible for failing to stop payment on the item. If the stop payment order is not received in time for the Credit Union to act upon the order, the Credit Union will not be liable to you or to any other party for payment of the item. If we recredit your account after paying a check over a valid and timely stop payment order, you agree to sign a statement describing the dispute with the payee, to transfer all of your rights against the payee or other holders of the check to the Credit Union, and to assist the Credit Union in legal action taken against the person.

  • Payment Requests Review applications for payment with Contractor for compliance with the established procedure for their submission and forward with recommendations to Engineer, noting particularly the relationship of the payment requested to the schedule of values, Work completed, and materials and equipment delivered at the Site but not incorporated in the Work.

  • Stop Payment Requests If you desire to stop any transfer that has already been processed, you must contact customer care for the Service pursuant to Section 22 of the General Terms. Although we will make a reasonable effort to accommodate your request, we will have no liability for failing to do so. We may also require you to present your request in writing within fourteen (14) days. The charge for each request will be the current charge for such service as set out in the applicable fee schedule.

  • Disbursement Requests Except as expressly provided in the Credit Agreement, Administrative Agent must receive Disbursement Requests in writing. Disbursement Requests will only be accepted from the applicable Authorized Representatives designated in the Disbursement Instruction Agreement. Disbursement Requests will be processed subject to satisfactory completion of Administrative Agent’s customer verification procedures. Administrative Agent is only responsible for making a good faith effort to execute each Disbursement Request and may use agents of its choice to execute Disbursement Requests. Funds disbursed pursuant to a Disbursement Request may be transmitted directly to the Receiving Bank, or indirectly to the Receiving Bank through another bank, government agency, or other third party that Administrative Agent considers to be reasonable. Administrative Agent will, in its sole discretion, determine the funds transfer system and the means by which each Disbursement will be made. Administrative Agent may delay or refuse to accept a Disbursement Request if the Disbursement would: (i) violate the terms of this Agreement; (ii) require use of a bank unacceptable to Administrative Agent or Lenders or prohibited by government authority; (iii) cause Administrative Agent or Lenders to violate any Federal Reserve or other regulatory risk control program or guideline; or (iv) otherwise cause Administrative Agent or Lenders to violate any applicable law or regulation.

  • Monthly Invoices Consultant shall prepare and submit invoices on a monthly basis by the tenth of each month, unless requested otherwise by the City’s Contract Manager. The invoices shall be accompanied by the Monthly Progress Report that describes the work completed during the invoice’s billing period.

  • Payment Calculation District shall pay Contractor at a rate of $ per . District shall pay Contractor as described in attached Exhibit A

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • Milestone Payment The first time Net Sales in the Territory in a Royalty Period exceed US$[***] ([***] dollars) US$[***] ([***] dollars)

  • Milestone A principal event specified in the Contract Documents including the Material Completion and Occupancy Date and other events relating to an intermediate completion date or time.