Common use of CONTRACTOR’S CONSTRUCTION SCHEDULES Clause in Contracts

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 5 contracts

Samples: Immunicon Corp, Agreement (Digex Inc/De), Contract for Construction (Monarch Casino & Resort Inc)

AutoNDA by SimpleDocs

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 § 9.8.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's ’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 4 contracts

Samples: www.wiltonct.org, www.gov.bm, www.greenfieldin.org

CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's ’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 3 contracts

Samples: Indemnity Agreement, www.fitnyc.edu, bidcondocs.delaware.gov

CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 2 contracts

Samples: 70.248.29.17:8085, STAMPS.COM Inc

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 § 9.8.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's ’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 2 contracts

Samples: themuseumschool.org, www.gov.bm

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's ’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 1 contract

Samples: Form of Agreement

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 § 9.8.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s approval and Architect's ’s information a Contractor's construction schedule ’s Construction Schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 1 contract

Samples: homeforward.org

AutoNDA by SimpleDocs

CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the ContractContract (and in a time not to exceed thirty (30) days), shall prepare and submit for the Owner's ’s and Architect's Engineer’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 1 contract

Samples: rubybids.ruby-collins.com

CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's Engineer’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 1 contract

Samples: mccmeetingspublic.blob.core.usgovcloudapi.net

CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's Owner and Architect's information approval a Contractor's critical path construction schedule for the Work. The schedule shall conform to and shall not exceed time limits current required under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and ProjectContract Documents, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

Appears in 1 contract

Samples: www.spotsylvania.k12.va.us:443