CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. 3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals. 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
Appears in 1 contract
Samples: Lease Agreement (Immunicon Corp)
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated coordi- nated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with conform to the most recent schedules submitted to the Owner and Architectschedules.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and find keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with conform to the most recent schedules submitted to the Owner and Architectschedules.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's ’s and Architect's ’s information a Contractor's ’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's ’s approval, a schedule of submittals which is coordinated with the Contractor's ’s construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
Appears in 1 contract
Samples: Construction Contract
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with conform to the most recent schedules submitted to the Owner and Architectschedules.
Appears in 1 contract
Samples: Construction Contract (Monarch Casino & Resort Inc)