Contractor’s Markup on Subcontractor’ Work. The Contractor's management markup on the subcontractor's net additional allowable expenditures shall be seven and one half percent. The Contractor shall not be permitted the overhead and profit markup on Time Dependent Overhead Costs, but shall be permitted a management markup of five percent on Time Dependent Overhead Costs.
Appears in 44 contracts
Samples: Design Bid Build Construction Contract, Design Bid Build Construction Contract, Design Bid Build Construction Contract
Contractor’s Markup on Subcontractor’ Work. The Contractor's management markup on the subcontractor's net additional allowable expenditures shall be seven and one seven-and-one-half percent. The Contractor shall not be permitted the overhead and profit markup on Time Dependent Overhead Costs, Costs but shall be permitted a management markup of five percent on Time Dependent Overhead Costs.
Appears in 10 contracts
Samples: Construction Contract, Construction Contract, Construction Contract