Contractor’s Submittals. 8.3.1 General: Include within the Construction Schedule a schedule for submittals ("submittal schedule") in accordance with Contract Time and Contract Document requirements. XXXX shall prepare and submit a progress schedule for himself, each sub-contractor and supplier, showing anticipated dates for submittals of construction data. Schedule shall allow for lead time required for subcontractors, material and equipment manufacturers, fabricators and suppliers, delivery of materials and equipment, in sufficient time for installation without delaying any portion of the work.

Appears in 4 contracts

Samples: Construction Manager at Risk Construction Contract, Risk Construction Agreement, Construction Manager at Risk Construction Contract

AutoNDA by SimpleDocs

Contractor’s Submittals. 8.3.1 General: Include within the Construction Schedule a schedule for submittals ("submittal schedule") in accordance with Contract Time and Contract Document requirements. XXXX CM shall prepare and submit a progress schedule for himself, each sub-contractor and supplier, showing anticipated dates for submittals of construction data. Schedule shall allow for lead time required for subcontractors, material and equipment manufacturers, fabricators and suppliers, delivery of materials and equipment, in sufficient time for installation without delaying any portion of the work.

Appears in 2 contracts

Samples: Construction Phase Services, Construction Phase Services

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.