Coordination of the Funding Plan with Transmission Plan Sample Clauses

Coordination of the Funding Plan with Transmission Plan. Through the Funding Process, the Parties shall have the opportunity to review and provide comments to DSW on its Desert Southwest Region Systems Transmission Plan through the procedures identified in [Attachment A]. 6.2.9.1. Transmission projects that go through DSW’s Analysis of Alternatives (AoA) process shall be discussed by DSW with the Parties, and DSW shall determine, with input from the Parties, if a particular transmission project should be revised or included in the TYP. The Parties may offer alternatives to projects going through the AoA process to WAPA and/or DSW, and such alternatives shall be considered by WAPA and/or DSW prior to completion of the AoA process. 6.2.9.2. Funding for projects identified in the Transmission Planning shall be voted on through the TYP when it is determined that the project shall be included in the TYP. 6.2.9.3. Nothing in the Transmission Planning process enables any facility, system, electrically interconnected to the Desert Southwest Region System to be added to the Xxxxxx-Xxxxx Project or Intertie Project rates or affect other Desert Southwest Region Systems costs or rates.
AutoNDA by SimpleDocs

Related to Coordination of the Funding Plan with Transmission Plan

  • Information Submission by Connecting Transmission Owner The initial information submission by Connecting Transmission Owner shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include New York State Transmission System information necessary to allow the Developer to select equipment and meet any system protection and stability requirements, unless otherwise mutually agreed to by the Developer and Connecting Transmission Owner. On a monthly basis Connecting Transmission Owner shall provide Developer and NYISO a status report on the construction and installation of Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report; (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.

  • Implementation of Corrective Action Plan After the Corrective Action Plan is finalized, the Purchasers shall use reasonable best efforts to implement the finalized Corrective Action Plan on the timeline set forth therein and provide periodic reports (as provided for therein) to the Sellers on the status of their implementation of the Corrective Action Plan.

  • Transmission Delivery Service Implications Under ER Interconnection Service, Interconnection Customer will be eligible to inject power from the Generating Facility into and deliver power across the Transmission System on an “as available” basis up to the amount of MW identified in the applicable stability and steady state studies to the extent the upgrades initially required to qualify for ER Interconnection Service have been constructed. After that date FERC makes effective MISO’s Energy Market Tariff filed in Docket No. ER04-691-000, Interconnection Customer may place a bid to sell into the market up to the maximum identified Generating Facility output, subject to any conditions specified in the Interconnection Service approval, and the Generating Facility will be dispatched to the extent the Interconnection Customer’s bid clears. In all other instances, no transmission or other delivery service from the Generating Facility is assured, but Interconnection Customer may obtain Point-To-Point Transmission Service, Network Integration Transmission Service or be used for secondary network transmission service, pursuant to the Tariff, up to the maximum output identified in the stability and steady state studies. In those instances, in order for Interconnection Customer to obtain the right to deliver or inject energy beyond the Point of Interconnection or to improve its ability to do so, transmission delivery service must be obtained pursuant to the provisions of the Tariff. The Interconnection Customer’s ability to inject its Generating Facility output beyond the Point of Interconnection, therefore, will depend on the existing capacity of the Transmission or Distribution System as applicable, at such time as a Transmission Service request is made that would accommodate such delivery. The provision of Firm Point-To-Point Transmission Service or Network Integration Transmission Service may require the construction of additional Network or Distribution Upgrades.

  • Data Transmission Control Except as necessary for the provision of the Cloud Services in accordance with the Agreement, Personal Data must not be read, copied, modified or removed without authorization during transfer. Where data carriers are physically transported, adequate measures are implemented at SAP to provide the agreed-upon service levels (for example, encryption and lead-lined containers).

  • Completion of Concrete Pours and Emergency Work (a) Except as provided in this sub-clause an Employee shall nor work or be required to work in the rain. (b) Employees shall not be required to start a concrete pour in Inclement Weather. (c) Where a concrete pour has been commenced prior to the commencement of a period of Inclement Weather Employees may be required to complete such concrete pour to a practical stage and for such work shall be paid at the rate of double time calculated to the next hour, and in the case of wet weather shall be provided with adequate wet weather gear. (d) If an Employee’s clothes become wet as a result of working in the rain during a concrete pour the Employee shall, unless the Employee has a change of dry working clothes available, be allowed to go home without loss of pay. (e) The provisions of clauses 32.7(c) and 32.7(d) hereof shall also apply in the case of emergency work where the Employees concerned and their delegates agree that the work is of an emergency nature and can start and/or proceed.

  • Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.

  • Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner [shall/shall not] transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.

  • Implementation Plan The Authority shall cause to be prepared an Implementation Plan meeting the requirements of Public Utilities Code Section 366.2 and any applicable Public Utilities Commission regulations as soon after the Effective Date as reasonably practicable. The Implementation Plan shall not be filed with the Public Utilities Commission until it is approved by the Board in the manner provided by Section 4.9.

  • Implementation Report Within 150 days after the Effective Date, Ensign Group shall submit a written report to OIG summarizing the status of its implementation of the requirements of this CIA (Implementation Report). The Implementation Report shall, at a minimum, include: 1. the name, address, phone number, and position description of the Compliance Officer required by Section III.A, and a summary of other noncompliance job responsibilities the Compliance Officer may have; 2. the names and positions of the members of the Compliance Committee required by Section III.A; 3. the names and positions of the members of the Board of Directors who are responsible for satisfying the Board of Directors compliance obligations described in Section III.A.3; 4. a copy of Ensign Group’s Code of Conduct required by Section III.B.1; 5. the number of individuals required to complete the Code of Conduct certification required by Section III.B.1, the percentage of individuals who have completed such certification, and an explanation of any exceptions (the documentation supporting this information shall be available to OIG upon request); 6. a summary of all Policies and Procedures required by Section III.B (copies of the Policies and Procedures shall be made available to OIG upon request); 7. the following information regarding each type of training required by Section III.C: a. a description of such training, including a summary of the topics covered, the length of sessions, and a schedule of training sessions; b. the number of individuals required to be trained, percentage of individuals actually trained, and an explanation of any exceptions. A copy of all training materials and the documentation supporting this information shall be made available to OIG upon request. 8. a description of the Disclosure Program required by Section III.E; 9. the following information regarding the IRO(s): (a) identity, address, and phone number; (b) a copy of the engagement letter; (c) information to demonstrate that the IRO has the qualifications outlined in Appendix A to this CIA; (d) a summary and description of any and all current and prior engagements and agreements between Ensign Group and the IRO; and (e) a certification from the IRO regarding its professional independence and objectivity with respect to Ensign Group; 10. a description of the process by which Ensign Group fulfills the requirements of Section III.F regarding Ineligible Persons; 11. a list of all of Ensign Group’s locations (including locations and mailing addresses); the corresponding name under which each location is doing business; the corresponding phone numbers and fax numbers; each location’s Medicare and state Medicaid program provider number and/or supplier number(s); and the name and address of each Medicare and state Medicaid program contractor to which Ensign Group currently submits claims; 12. a description of Ensign Group’s corporate structure, including identification of any parent and sister companies, subsidiaries, and their respective lines of business; and

  • Connecting Transmission Owner Obligations Connecting Transmission Owner shall maintain its transmission facilities and Attachment Facilities in a safe and reliable manner and in accordance with this Agreement.