Cost of Change Orders. Within Ten (10) days after a request for any such change or event causing a change or such lesser period of time as may be reasonably required by GCCS, TMG shall provide GCCS, in writing, an estimate of the effect of the proposed Change Order upon the Contract Price and the actual cost of construction, which shall include a complete itemized cost breakdown. Changes may be made by GCCS by an appropriate written Change Order or at GCCS’s option such changes shall be implemented immediately upon TMG’s receipt of an appropriate Construction Change Directive.
Appears in 1 contract
Samples: Construction Contract