Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to: (a) the design of the Project; (b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards; (c) improper maintenance during construction of the Project Highway by the Contractor; and/ or (d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 34 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.215.2, including any additional testingtests, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Works, Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Project Highway by the Contractor; and/ or
(d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 9 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.215.2, including any additional testingtests, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Works, Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Railway Project Highway by the Contractor; and/ or
(d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 8 contracts
Samples: Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.215.2, including any additional testingtests, shall be carried out by the Contractor at its own risk and & cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Plantworks, Materials plant, materials or workmanship not being in accordance with this Agreement and the Specifications and & Standards;
(c) improper maintenance during construction of the Railway Project Highway by the Contractor; and/ or
(d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the The design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper Improper maintenance during construction of the Project Highway Works by the Contractor; and/ or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Contract Agreement for Design and Construction
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the The design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper Improper maintenance during construction of the Project Highway by the Contractor; and/ or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the The design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper Improper maintenance during construction of the Project Highway Works by the Contractor; and/ or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction Agreement, Demonstration Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Project Highway by the Contractor; and/ or
(d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 2 contracts
Samples: Draft Agreement for RFP for Beautification of Streets, Epc Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Project Highway by the Contractor; and/ or
(d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Construction Contract
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the The design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper Improper operation and maintenance during construction of the Project Highway Works by the Contractor; and/ or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Epc Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.216.2, including any additional testingTests, shall be carried out by the Contractor Concessionaire at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Works, Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction Construction of the Railway Project Highway by the ContractorConcessionaire; and/ or
(d) failure by the Contractor Concessionaire to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Concession Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification or replacement of any/all units of project undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or and repair is attributable to:
(a) the The design of the Project;:
(b) Plant, Materials or workmanship Workmanship not being in accordance with this Agreement agreement and the Specifications and Standards;
(c) improper maintenance Improper Maintenance during construction Construction of the Project Highway Works by the Contractor; and/ orand/or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreementagreement.
Appears in 1 contract
Samples: Epc Contract
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.216.2, including any additional testingtests, shall be carried out by the Contractor Concessionaire at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Works, Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Railway Project Highway by the ContractorConcessionaire; and/ or
(d) failure by the Contractor Concessionaire to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Concession Agreement
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Project Highway PROJECT by the Contractor; and/ or
(d) failure Failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 1 contract
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.2, including any additional testing, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Plant, Materials or workmanship not being in accordance with this Agreement and the Specifications and Standards;
(c) improper maintenance during construction of the Project Highway by the Contractor; and/ or
or (d) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Construction Contract
Cost of remedying Defects. For the avoidance of doubt, any repair or rectification undertaken in accordance with the provisions of Clause 17.215.2, including any additional testingtests, shall be carried out by the Contractor at its own risk and cost, to the extent that such rectification or repair is attributable to:
(a) the design of the Project;
(b) Works, Plant, Materials or workmanship not being in accordance with this Agreement and the the
(c) Specifications and Standards;
(cd) improper maintenance during construction of the Railway Project Highway by the Contractor; and/ or
(de) failure by the Contractor to comply with any other obligation under this Agreement.
Appears in 1 contract
Samples: Epc Agreement