Covered Or Concealed Work. If a portion of the Work has been covered, the General Contractor shall, if notified to do so by the Owner or a Professional, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner or the Professional, or to requirements specifically expressed in the Construction Documents, the General Contractor shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner or the Professional that it remain uncovered, the General Contractor shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Covered Or Concealed Work. If a portion of the Work has been covered, the DB shall, if notified to do so by the Owner, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner, or to requirements specifically expressed in the Construction Documents, the DB shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner that it remain uncovered, the DB shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Covered Or Concealed Work. If a portion of the Work has been covered, the Contractor shall, if notified to do so by the Owner’s Project Representative or a Professional, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner’s Project Representative or the Professional, or to requirements specifically expressed in the Construction Documents, the Contractor shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner’s Project Representative or the Professional that it remain uncovered, the Contractor shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Covered Or Concealed Work. If a portion of the Work has been covered, the Construction Manager shall, if notified to do so by the County or the Professional, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the County or the Professional, or to requirements specifically expressed in the Construction Documents, the Construction Manager will receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the County or the Professional that it remain uncovered, the Construction Manager will receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedules only if the designated portion of the Work was in conformance with the Construction Documents.
Covered Or Concealed Work. If a portion of the Work has been covered, the Builder shall, if notified to do so by the Owner or a Professional, uncover the designated portion for observation and then replace it.