Data and Information Exchange. Each Party shall provide the other PartiesParty with the following data and information for its Planning Coordinator area, as applicable, as follows.. Unless otherwise indicated, such data and information shall be provided as requested by either Party and as available, on a mutually agreed to schedule but no longer than 60 days from the date of such request. 8.39.2.1 Data required for the development of load flow cases, short-circuit cases, and stability cases for the Parties’ Planning Coordinator areas, as applicable, including ten- year load forecasts, including all critical assumptions that are used in the development of these cases. 8.39.2.2 Fully detailed planning models (up to the next ten (10) years) for the Parties’ Planning Coordinator areas, as applicable, as requested by any of the Parties and on a mutually agreed schedule as a part of the development of any joint planning studies provided for under this Article EightNine or as otherwise agreed to. 89.2.3.3 The regional plan document produced by the Party, any long-term or short- term reliability assessment documents produced by the Party, and any operating assessment reports produced by the Party. 8.39.2.4 The status of expansion studies, System Impact Studies,system impact studies and generation interconnection studies, such that each Party has knowledge that a commitment has been made to a system enhancement as a result of any such studies. 8.39.2.5 Transmission system maps for the Party’s bulk transmission system and lower voltage transmission system maps that are relevant to the coordination of planning between or among the systems. 8.39.2.6 Contingency lists for use in load flow and stability analyses, including lists of all single contingency events and multiple facility tower line contingencies, as well as breaker diagrams for the portions of the Party’s transmission system that are relevant to the coordination of planning between or among the systems. 8.39.2.7 The timing of each planned enhancement, including estimated start and completion dates and project mobilization schedules, and indications of the likelihood a system enhancement shallwill be completed and whether the system enhancement should be included in system expansion studies, System Impact Studies,system impact studies and generation interconnection studies, and all related applications for regulatory approval and the status thereof. This information shall be provided annually and from time to time upon changes in status.
Appears in 2 contracts
Samples: Joint Reliability Coordination Agreement, Joint Reliability Coordination Agreement
Data and Information Exchange. Each Party shall provide the other PartiesParty Parties with the following data and information for its Planning Coordinator area, as applicable, as follows.. . Unless otherwise indicated, such data and information shall be provided as requested by either Party and as available, on a mutually agreed to schedule but no longer than 60 days from the date of such request.
8.39.2.1 8.3.1 Data required for the development of load flow cases, short-circuit cases, and stability cases for the Parties’ Planning Coordinator areas, as applicable, including ten- ten-year load forecasts, including all critical assumptions that are used in the development of these cases.
8.39.2.2 8.3.2 Fully detailed planning models (up to the next ten (10) years) for the Parties’ Planning Coordinator areas, as applicable, as requested by any of the Parties and on a mutually agreed schedule as a part of the development of any joint planning studies provided for under this Article EightNine Eight or as otherwise agreed to.
89.2.3.3 8.3.3 The regional plan document produced by the Party, any long-term or short- short-term reliability assessment documents produced by the Party, and any operating assessment reports produced by the Party.
8.39.2.4 8.3.4 The status of expansion studies, System Impact Studies,system impact studies , and generation interconnection studies, such that each Party has knowledge that a commitment has been made to a system enhancement as a result of any such studies.
8.39.2.5 8.3.5 Transmission system maps for the Party’s bulk transmission system and lower voltage transmission system maps that are relevant to the coordination of planning between or among the systems.
8.39.2.6 8.3.6 Contingency lists for use in load flow and stability analyses, including lists of all single contingency events and multiple facility tower line contingencies, as well as breaker diagrams for the portions of the Party’s transmission system that are relevant to the coordination of planning between or among the systems.
8.39.2.7 8.3.7 The timing of each planned enhancement, including estimated start and completion dates and project mobilization schedulesdates, and indications of the likelihood a system enhancement shallwill shall be completed and whether the system enhancement should be included in system expansion studies, System Impact Studies,system impact studies , and generation interconnection studies, and all related applications for regulatory approval and the status thereof.
8.3.8 Load flow and short-circuit data initially shall be exchanged by the Parties in mutually agreed formats. This information To the extent practical, the maintenance and exchange of power system modeling data shall be implemented through in mutually agreed formats. When feasible, transmission maps and breaker diagrams shall be provided annually and in an electronic format agreed upon by the Parties. Formats for the exchange of other data shall be agreed upon by the Parties from time to time upon changes in statustime.
Appears in 2 contracts
Samples: Joint Reliability Coordination Agreement, Joint Reliability Coordination Agreement