Delay Payments. 29.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 7.1 (Charges and Invoicing) shall apply in relation to the payment of Delay Payments. 29.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where:
Appears in 4 contracts
Samples: Model Services Contract, Model Services Contract, Model Services Contract
Delay Payments. 29.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 7.1 (Charges and Invoicing) shall apply in relation to the payment of Delay Payments.
29.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where:
Appears in 1 contract
Samples: Services Agreement
Delay Payments. 29.1 If 1If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph paragraph 1 of Part C part 3 of Schedule schedule 7.1 (Charges and Invoicing) shall apply in relation to the payment of Delay Payments.
29.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where:
Appears in 1 contract
Samples: Agreement for the Provision of Infrastructure, Applications and Related Ict Services
Delay Payments. 29.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C B of Schedule 7.1 (Charges and Invoicing) shall apply in relation to the payment of Delay Payments.
29.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where:
Appears in 1 contract
Delay Payments. 29.1 28.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 7.1 15 (Charges and Invoicing) shall apply in relation to the payment of Delay Payments.
29.2 28.2 Delay Payments shall be the AuthorityNetwork Rail's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where:
Appears in 1 contract
Samples: It Solutions and System Integration Services Agreement