Common use of Delays Beyond Contractor's Control Clause in Contracts

Delays Beyond Contractor's Control. A. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of CONTRACTOR, the Contract Times (or Milestones) will be extended in an amount equal to the time lost due to such CONTRACTOR. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of CONTRACTOR.

Appears in 6 contracts

Samples: Agreement, Agreement, Agreement