Common use of Delays during Implementation Clause in Contracts

Delays during Implementation. a) The Concessionaire may apply for an extension in Construction Period if it is reasonably sure and anticipates that it shall be delayed in achieving the Scheduled Completion Date, by any of the following causes:-

Appears in 4 contracts

Samples: Draft Concession Agreement, Draft Concession Agreement, Draft Concession Agreement

AutoNDA by SimpleDocs

Delays during Implementation. a) The Concessionaire may apply for an extension in Construction Period if it is reasonably sure and anticipates that it shall be delayed in achieving the Scheduled Completion Date, by any of the following causes:-causes:

Appears in 3 contracts

Samples: Draft Concession Agreement, Draft Concession Agreement, Draft Concession Agreement

AutoNDA by SimpleDocs

Delays during Implementation. a) a. The Concessionaire may apply for an extension in Construction Period if it is reasonably sure and anticipates that it shall be delayed in achieving the Scheduled Completion Date, by any of the following causes:-causes:

Appears in 1 contract

Samples: Concession Agreement