DESIGN-BUILDER’S DESIGN AND CONSTRUCTION SCHEDULES. 3.9.1 The Design-Builder will be responsible for the planning, scheduling and coordination of all Work performed under the Contract Documents and the entire Project as a whole so that materials will arrive on schedule and Work will proceed without delay. 3.9.2 The Design-Builder will submit preliminary and baseline design and construction schedules for Owner’s review and approval in accordance with requirements specified under General Requirements Section 01315 - SCHEDULES, PHASING. These schedules will not exceed time limits set forth in the Contract Documents, will be revised at appropriate intervals as required by the conditions of the Work and Project (but not less frequently than monthly), will be related to the entire Project to the extent required by the Contract Documents and will provide for expeditious and practicable execution of the Work. These schedules and any subsequent changes thereto will be incorporated into the Contract Documents by reference. 3.9.3 The Design-Builder will prepare and keep current, for the Owner’s approval, a schedule of submittals which is coordinated with the Design-Builder’s design and construction schedule and allows the Owner reasonable time to review submittals. 3.9.4 The Design-Builder will conform to the most recent approved schedules.
Appears in 7 contracts
Samples: Contract for Design Build Services, Design Build Services Contract, Contract for Design Build Services