Design Phase Milestone Schedule. After the Owner accepts the Master Schedule the CM shall prepare a Milestone Schedule for the Design Phase. The Design Phase Milestone Schedule may be used in the request for proposals and contract for the Designer and shall be a method for judging progress during the Design Phase. THE CM SHALL TRACK THE DESIGNER’S PROGRESS DURING THE DESIGN PHASE AND ALERT THE OWNER OF ANY DELAYS IN THE DESIGNER’S TIMELY COMPLETION OF ITS SERVICES.
Appears in 3 contracts
Samples: Standard Form of Agreement Between Owner and Construction Manager (Construction Manager at Risk), Standard Form of Agreement Between Owner and Construction Manager (Construction Manager at Risk), Standard Form of Agreement Between Owner and Construction Manager (Construction Manager at Risk)
Design Phase Milestone Schedule. After In accordance with the Construction Management Plan, after the Owner accepts the Master Schedule the CM shall prepare a Milestone Schedule for the Design Phase. The Design Phase Milestone Schedule may shall be used in the request for proposals and contract for the Designer and shall be a method for judging progress during the Design Phase. THE The Design Phase Milestone Schedule activities shall include schematic design documents, design development documents, construction documents, permitting, creation of separate specifications and bid packages, and selection and approval of long-lead-time components of the Project. The CM SHALL TRACK THE DESIGNER’S PROGRESS DURING THE DESIGN PHASE AND ALERT THE OWNER OF ANY DELAYS IN THE DESIGNER’S TIMELY COMPLETION OF ITS SERVICESshall monitor compliance with the Design Phase Milestone Schedule, and promptly notify the Owner and Designer of any delay or change in the Design Phase Milestone Schedule.
Appears in 3 contracts
Samples: Architect Contract, Construction Management Agreement, Construction Management Agreement
Design Phase Milestone Schedule. After In accordance with the Construction Management Plan, after the Owner accepts the Master School Project Schedule the CM shall prepare a Milestone Schedule for the Design Phase. The Design Phase Milestone Schedule may shall be used in the request for proposals and contract for the Designer and shall be a method for judging progress during the Design Phase. THE The Design Phase Milestone Schedule activities shall include schematic design documents, design development documents, construction documents, permitting, creation of separate specifications and bid packages, and selection and approval of long-lead-time components of the Project. The CM SHALL TRACK THE DESIGNER’S PROGRESS DURING THE DESIGN PHASE AND ALERT THE OWNER OF ANY DELAYS IN THE DESIGNER’S TIMELY COMPLETION OF ITS SERVICESshall monitor compliance with the Design Phase Milestone Schedule, and promptly notify the Owner and Designer of any delay or change in the Design Phase Milestone Schedule.
Appears in 1 contract
Samples: Architect Contract