Design Professional Services. 3.3.1 All design services required by this Contract will be performed by appropriately licensed architects, engineers and other licensed design professionals. The contractual obligations of such professional persons or entities are undertaken and performed in the interest of the Design-Builder and the Owner. 3.3.2 The Design-Builder will submit, at a minimum, the 90% and 100% Project Documents for review, comment and approval by the Owner. Project Documents will consist of all Drawings, Specifications, electronic data and other documents sufficient to establish the size, quality and character of the entire Project, its architectural, civil, structural, mechanical and electrical systems, materials and such other elements of the Project as may be appropriate and will: 3.3.2.1 Be consistent with the intent of the Design-Builder’s GMP Proposal Documents 3.3.2.2 Provide information for the use of those in the building trades; 3.3.2.3 Include documents customarily required for regulatory agency approvals; 3.3.2.4 Be consistent with the intent of the current version Owner’s Design Criteria Manual. Any deviations from the Owner’s Design Criteria Manual must be separately highlighted and disclosed by Design-Builder and approved in writing by Owner with each applicable submittal. Owner approval of Project Documents does not relieve or release Design-Builder of any of its responsibilities or liability for the Project Documents. 3.3.3 Prior to starting the Work and at frequent intervals during the progress thereof, the Design-Builder will carefully study and compare the Contract Documents with each other and with the information furnished by the Owner and will at once report to the Owner any error, inconsistency or omission the Design-Builder may discover. Any necessary change will be accomplished as provided in Article 8. 3.3.4 The Design-Builder will take field measurements and verify field conditions and will carefully compare such field measurements, field conditions and other information known to the Design-Builder with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered will be reported to the Owner at once. 3.3.5 The Design-Builder will give the Owner timely written notice of all additional information or instructions required from the Owner to define the Work in greater detail or to permit the proper progress of the Work. 3.3.6 If the Design-Builder proceeds with the Work without such notice to the Owner, having discovered such errors, inconsistencies or omissions, or if by reasonable study of the Contract Documents the Design-Builder could have discovered such, the Design-Builder will bear all increased or additional costs arising therefrom without reimbursement from the Owner. 3.3.7 In the event that Design-Builder seeks to change the staffing of the Project Manager(s) or Superintendent(s) named in the GMP proposal, the Design-Builder shall provide written notice no later than 30 days prior to the proposed staffing change with the proposed change, detailed resume and work history for the proposed replacement, the reasoning for the proposed change and a detailed transition plan. The Owner shall approve or disapprove the proposed change within 10 days following the date of receipt of Design-Builder’s notice. Such approval shall not be unreasonably withheld. The Owner reserves the right to declare Design- Builder in breach if it fails to use proposed or approved staffing.
Appears in 6 contracts
Samples: Contract for Design Build Services, Design Build Services Contract, Contract for Design Build Services
Design Professional Services. 3.3.1 All design services required by this Contract will be performed by appropriately licensed architects, engineers and other licensed design professionals. The contractual obligations of such professional persons or entities are undertaken and performed in the interest of the Design-Builder Contractor and the Owner.
3.3.2 The Design-Builder Contractor will submit, at a minimum, the 90% and 100% submit Project Documents for review, comment and approval by the Owner, as agreed by the Parties. Project Documents will consist of all Drawings, Specifications, electronic data and other documents sufficient to establish the size, quality and character of the entire Project, its architectural, civil, structural, mechanical and electrical systems, materials and such other elements of the Project as may be appropriate and will:
3.3.2.1 Be consistent with the intent of the Design-BuilderContractor’s GMP Proposal Documents
3.3.2.2 Provide information for the use of those in the building trades;
3.3.2.3 Include documents customarily required for regulatory agency approvals;
3.3.2.4 Be consistent with the intent of the current version Owner’s Design Criteria Manual. Any deviations from the Owner’s Design Criteria Manual must be separately highlighted and disclosed by Design-Builder Contractor and approved in writing by Owner with each applicable submittal. Owner approval of Project Documents does not relieve or release Design-Builder Contractor of any of its responsibilities or liability for the Project Documents.
3.3.3 Prior to starting the Work and at frequent intervals during the progress thereof, the Design-Builder Contractor will carefully study and compare the Contract Documents with each other and with the information furnished by the Owner and will at once report to the Owner any error, inconsistency or omission the Design-Builder Contractor may discover. Any necessary change will be accomplished as provided in Article 8.
3.3.4 The Design-Builder Contractor will take field measurements and verify field conditions and will carefully compare such field measurements, field conditions and other information known to the Design-Builder Contractor with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered will be reported to the Owner at once.
3.3.5 The Design-Builder Contractor will give the Owner timely written notice of all additional information or instructions required from the Owner to define the Work in greater detail or to permit the proper progress of the Work.
3.3.6 If the Design-Builder Contractor proceeds with the Work without such notice to the Owner, having discovered such errors, inconsistencies or omissions, or if by reasonable study of the Contract Documents the Design-Builder Contractor could have discovered such, the Design-Builder Contractor will bear all increased or additional costs arising therefrom without reimbursement from the Owner.
3.3.7 In the event that Design-Builder Contractor seeks to change the staffing of the Project Manager(s) or Superintendent(s) named in the GMP proposal, the Design-Builder Contractor shall provide written notice no later than 30 days prior to the proposed staffing change with the proposed change, detailed resume and work history for the proposed replacement, the reasoning for the proposed change and a detailed transition plan. The Owner shall approve or disapprove the proposed change within 10 days following the date of receipt of Design-BuilderContractor’s notice. Such approval shall not be unreasonably withheld. The Owner reserves the right to declare Design- Builder Contractor in breach if it fails to use proposed or approved staffing.
Appears in 1 contract
Samples: Contract for Services
Design Professional Services. 3.3.1 All design services required by this Contract will be performed by appropriately licensed architects, engineers and other licensed design professionals. The contractual obligations of such professional persons or entities are undertaken and performed in the interest of the Design-Builder and the Owner.
3.3.2 The Design-Builder will submit, at a minimum, the 90% and 100% Project Documents for review, comment and approval by the Owner. Project Documents will consist of all Drawings, Specifications, electronic data and other documents sufficient to establish the size, quality and character of the entire Project, its architectural, civil, structural, mechanical and electrical systems, materials and such other elements of the Project as may be appropriate and will:
3.3.2.1 Be consistent with the intent of the Design-Builder’s GMP Proposal Documents
3.3.2.2 Provide information for the use of those in the building trades;
3.3.2.3 Include documents customarily required for regulatory agency approvals;
3.3.2.4 Be consistent with the intent of the current version Owner’s Design Criteria Manual. Any deviations from the Owner’s Design Criteria Manual must be separately highlighted and disclosed by Design-Builder and approved in writing by Owner with each applicable submittal. Owner approval of Project Documents does not relieve or release Design-Builder of any of its responsibilities or liability for the Project Documents.
3.3.3 Prior to starting the Work and at frequent intervals during the progress thereof, the Design-Builder will carefully study and compare the Contract Documents with each other and with the information furnished by the Owner and will at once report to the Owner any error, inconsistency or omission the Design-Builder may discover. Any necessary change will be accomplished as provided in Article 8.
3.3.4 The Design-Builder will take field measurements and verify field conditions and will carefully compare such field measurements, field conditions and other information known to the Design-Builder with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered will be reported to the Owner at once.
3.3.5 The Design-Builder will give the Owner timely written notice of all additional information or instructions required from the Owner to define the Work in greater detail or to permit the proper progress of the Work.
3.3.6 If the Design-Builder proceeds with the Work without such notice to the Owner, having discovered such errors, inconsistencies or omissions, or if by reasonable study of the Contract Documents the Design-Builder could have discovered such, the Design-Builder will bear all increased or additional costs arising therefrom without reimbursement from the Owner.
3.3.7 In the event that Design-Builder seeks to change the staffing of the Project Manager(s) or Superintendent(s) named in the GMP proposal, the Design-Builder shall provide written notice no later than 30 days prior to the proposed staffing change with the proposed change, detailed resume and work history for the proposed replacement, the reasoning for the proposed change and a detailed transition plan. The Owner shall approve or disapprove the proposed change within 10 days following the date of receipt of Design-Builder’s notice. Such approval shall not be unreasonably withheld. The Owner reserves the right to declare Design- Builder in breach if it fails to use proposed or approved staffing.
Appears in 1 contract
Samples: Contract for Design Build Services
Design Professional Services. 3.3.1 All design services required by this Contract will be performed by appropriately licensed architects, engineers and other licensed design professionals. The contractual obligations of such professional persons or entities are undertaken and performed in the interest of the Design-Builder and the Owner.
3.3.2 The Design-Builder will submit, at a minimum, the 90% and 100% Project Documents for review, comment and approval by the Owner. Project Documents will consist of all Drawings, Specifications, electronic data and other documents sufficient to establish the size, quality and character of the entire Project, its architectural, civil, structural, mechanical and electrical systems, materials and such other elements of the Project as may be appropriate and will:
3.3.2.1 Be consistent with the intent of the Design-Builder’s GMP Proposal Documents
3.3.2.2 Provide information for the use of those in the building trades;
3.3.2.3 Include documents customarily required for regulatory agency approvals;
3.3.2.4 Be consistent with the intent of the current version Owner’s Design Criteria Manual. Any deviations Deviations from the Owner’s Design Criteria Manual must be separately highlighted and disclosed by Design-Builder and approved in writing by Owner with each applicable submittal. Owner approval of Project Documents does not relieve or release Design-Builder of any of its responsibilities or liability for the Project Documents.
3.3.3 Prior to starting the Work and at frequent intervals during the progress thereof, the Design-Design- Builder will carefully study and compare the Contract Documents with each other and with the information furnished by the Owner and will at once report to the Owner any error, inconsistency or omission the Design-Builder may discover. Any necessary change will be accomplished as provided in Article 8.
3.3.4 The Design-Builder will take field measurements and verify field conditions and will carefully compare such field measurements, field conditions and other information known to the Design-Builder with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered will be reported to the Owner at once.
3.3.5 The Design-Builder will give the Owner timely written notice of all additional information or instructions required from the Owner to define the Work in greater detail or to permit the proper progress of the Work.
3.3.6 If the Design-Builder proceeds with the Work without such notice to the Owner, having discovered such errors, inconsistencies or omissions, or if by reasonable study of the Contract Documents the Design-Builder could have discovered such, the Design-Builder will bear all increased or additional costs arising therefrom without reimbursement from the Owner.
3.3.7 In the event that Design-Builder seeks to change the staffing of the Project Manager(s) or Superintendent(s) named in the GMP proposal, the Design-Builder shall provide written notice no later than 30 days prior to the proposed staffing change with the proposed change, detailed resume and work history for the proposed replacement, the reasoning for the proposed change and a detailed transition plan. The Owner shall approve or disapprove the proposed change within 10 days following the date of receipt of Design-Builder’s notice. Such approval shall not be unreasonably withheld. The Owner reserves the right to declare Design- Design-Builder in breach if it fails to use proposed or approved staffing.
Appears in 1 contract
Samples: Design Build Contract