DESIGN PROFESSIONAL'S SERVICES. A. Pre-Design/Schematic Design Phase Design Professional shall: 1. identify applicable building codes, administrative, and permit processing requirements as relevant; 2. verify, by on-site inspection unless specifically stated otherwise by the Owner, existing conditions and systems, including but not necessarily limited to architectural, structural, mechanical and electrical systems, to confirm that these conditions and systems are of adequate condition and capacity to support the Work to be executed on the Project; 3. in consultation with Consultant team, Owner representatives, and other designated persons, use all available information to evaluate the program requirements, and with appropriate data and graphics propose a series of improvements deemed necessary and desirable to satisfy the program requirements, including; space needs, budget, availability of utilities, effect of codes and ordinances, safety and energy requirements, access to all spaces for all people, historical character of the building, and any other factors and design criteria identified by Owner, Consultant team or Design Professional.; 4. based on the most recent Owner approved program requirements, develop schematic design studies consisting of drawings, and other documents for the Owner's approval; 5. provide documents suitable for submission to the City of Corvallis for the Oregon State University Pre-Development Plan Review, as required the Owner; 6. provide to the Owner the required documents for the approval of various governmental agencies having jurisdiction over the Project; Owner shall pay for all required appeals and plan review fees; 7. submit to the Owner an estimate, consistent with the requirements of Section I.G.4 above and prepared by an independent cost estimator, of the probable Construction Budget of the Project based upon current area, volume or other appropriate unit costs, and compare and reconcile this independent cost estimate with a separate, independent cost estimate obtained by the Owner;
Appears in 2 contracts
Samples: Design Professional's Agreement, Design Professional's Agreement
DESIGN PROFESSIONAL'S SERVICES. A. Pre-Design/Schematic Design Phase Design Professional shall:
1. identify applicable building codes, administrative, and permit processing requirements as relevant;
2. verify, by on-site inspection unless specifically stated otherwise by the Owner, existing conditions and systems, including but not necessarily limited to architectural, structural, mechanical and electrical systems, to confirm that these conditions and systems are of adequate condition and capacity to support the Work to be executed on the Project;
3. in consultation with Consultant team, Owner representatives, and other designated persons, use all available information to evaluate the program requirements, and with appropriate data and graphics propose a series of improvements deemed necessary and desirable to satisfy the program requirements, including; space needs, budget, availability of utilities, effect of codes and ordinances, safety and energy requirements, access to all spaces for all people, historical character of the building, and any other factors and design criteria identified by Owner, Consultant team or Design Professional.;
4. based on the most recent Owner approved program requirements, develop schematic design studies consisting of drawings, and other documents for the Owner's approval;
5. provide documents suitable for submission to the City of Corvallis for the Oregon State University Pre-Development Plan Review, as required the Owner;
6. provide to the Owner the required documents for the approval of various governmental agencies having jurisdiction over the Project; Owner shall pay for all required appeals and plan review fees;
7. submit to the Owner an estimate, consistent with the requirements of Section I.G.4 above and prepared by an independent cost estimator, of the probable Construction Budget of the Project based upon current area, volume or other appropriate unit costs, and compare and reconcile this independent cost estimate with a separate, independent cost estimate obtained by the Owner;
8. if the Contractor for the Project is a CM/GC, the Design Professional shall perform the following Services associated with preparation of the probable Construction Budget of the Project:
a. In lieu of performing the Construction Budget estimating Services described in Section
Appears in 1 contract
Samples: Design Professional's Agreement
DESIGN PROFESSIONAL'S SERVICES. A. Pre-Design/Schematic Design Phase Design Professional shall:
1. identify applicable building codes, administrative, and permit processing requirements as relevant;
2. verify, by on-site inspection unless specifically stated otherwise by the Owner, existing conditions and systems, including but not necessarily limited to architectural, structural, mechanical and electrical systems, to confirm that these conditions and systems are of adequate condition and capacity to support the Work to be executed on the Project;
3. in consultation with Consultant team, Owner representatives, and other designated persons, use all available information to evaluate the program requirements, and with appropriate data and graphics propose a series of improvements deemed necessary and desirable to satisfy the program requirements, including; space needs, budget, availability of utilities, effect of codes and ordinances, safety and energy requirements, access to all spaces for all people, historical character of the building, and any other factors and design criteria identified by Owner, Consultant team or Design Professional.;
4. based on the most recent Owner approved program requirements, develop schematic design studies consisting of drawings, and other documents for the Owner's approval;
5. provide documents suitable for submission to the City of Corvallis for the Oregon State University Pre-Development Plan Review, as required the Owner;
6. provide to the Owner the required documents for the approval of various governmental agencies having jurisdiction over the Project; Owner shall pay for all required appeals and plan review fees;
7. submit Submit to the Owner an estimate, consistent with the requirements of Section I.G.4 above and prepared by an independent cost estimatorabove, of the probable Construction Budget of the Project based upon current area, volume or other appropriate unit costs, and compare and reconcile this independent cost estimate with a separate, independent cost estimate obtained by the Owner;
8. Submit to the Owner the following documents, information and other data:
a. preliminary fire life safety review document and associated plans;
b. general exterior materials and interior finishes recommendations, if applicable;
c. a Project schedule delineating the estimated time required for the Design Professional to complete the design development, construction documents, permitting and construction administration phases of the Project;