Determination of Cost. An increase or decrease in a GMP resulting from a change in the Work shall be determined by one or more of the following methods: A. Unit prices set forth in this Agreement or as subsequently agreed. B. Mutually accepted, itemized lump sum. C. Costs determined as defined in Article 3 above. D. If an increase or decrease cannot be agreed to as set forth in Subsections 8.4(A) and (B) and the City issues a written order for the Construction Manager to proceed with the change, the cost of the change in the Work shall be determined by the reasonable expense or savings of the performance of the Work resulting from the change.
Appears in 2 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Determination of Cost. An increase or decrease in a GMP resulting from a change in the Work shall be determined by one or more of the following methods:
A. Unit prices set forth in this Agreement or as subsequently agreed.
B. Mutually accepted, itemized lump sum.
C. Costs determined as defined in Article 3 above.
D. If an increase or decrease cannot be agreed to as set forth in Subsections 8.4(A) and (B) and the City District issues a written order for the Construction Manager to proceed with the change, the cost of the change in the Work shall be determined by the reasonable expense or savings of the performance of the Work resulting from the change.
Appears in 1 contract
Determination of Cost. An increase or decrease in a GMP resulting from a change in the Work shall be determined by one or more of the following methods:
A. Unit prices set forth in this Agreement or as subsequently agreed.
B. Mutually accepted, itemized lump sum.
C. Costs determined as defined in Article 3 above.
D. If an increase or decrease cannot be agreed to as set forth in Subsections 8.4(A) and (B) and the City Town issues a written order for the Construction Manager Contractor to proceed with the change, the cost of the change in the Work shall be determined by the reasonable expense or savings of the performance of the Work resulting from the change.
Appears in 1 contract
Samples: Design Build Agreement
Determination of Cost. An increase or decrease in a GMP resulting from a change in the Work shall will be determined by one or more of the following methods:
A. Unit prices set forth in this Agreement Contract or as subsequently agreed.
B. Mutually accepted, itemized lump sum.
C. Costs determined as defined in Article 3 above.
D. If an increase or decrease cannot be agreed to as set forth in Subsections 8.4(A) and (B) and the City AWC issues a written order for the Construction Manager to proceed with the change, the cost of the change in the Work shall will be determined by the reasonable expense or savings of the performance of the Work resulting from the change.