Development Period & Milestones Sample Clauses

Development Period & Milestones i) The Developer/licensee shall construct minimum 30% of the maximum Built-up area available within three years from the date of Development Agreement.
AutoNDA by SimpleDocs
Development Period & Milestones. (i) The Developer shall construct and complete minimum 20% of the Dwelling Units in all respect within three years from the date of issue of NoA .
Development Period & Milestones i. The Developer shall commence the development and construction works for Commercial Development by obtaining development and/or building permission as the case may be and all other permission/clearances/licenses required from the competent Authorities within a period of One (1) year from the date of issuance of NoA;
Development Period & Milestones. The Lessee shall construct and put in operation 250 bedded Multi super speciality hospital as per the IPHS and minimum standard laid down by the NABH and NABL in phased manner within 7 years of the signing of lease cum development agreement. The Selected Applicant shall have the following Development Milestones:
Development Period & Milestones i. The Licensee shall commence the development and construction works for Commercial Facility by obtaining development and/or building permission as the case may be and all other permission/clearances/licenses required from the competent Authorities within a period of One (1) year from the date of issuance of NoA;
Development Period & Milestones. The licensee shall have to complete the development of mandatory project and within 5 (Five) years from the date of issue of Notice of Award (NoA). The milestone of project are as follows:
Development Period & Milestones. (As per Clause 5. Schedule-A, Part-E - Minimum Development Obligations of the RFP document)
AutoNDA by SimpleDocs
Development Period & Milestones. The development milestone has been made in a way to ensure completion of 100 Bedded Hospital within 5 years of signing of Lease Agreement.
Development Period & Milestones i. The Lessee shall secure all the required approvals permissions, NOC from the competent authority to commence the construction of Health Facility within 12 (twelve) months from date of issue of Notice of Allotment.
Development Period & Milestones i. The Lessee shall secure all the required approvals permissions, NOC from the competent authority within 6 months from the date of issue of notice of award. In case Lessee fails to obtain the permissions or approval in 6 months, the time for obtaining the approvals may be extended for another term of 6 months without any penal charges at the sole discretion of the Lessor.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!