Eligible Changes. 10.3.1.1 DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows: (a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal; (b) Additional costs relating to Hazardous Materials, Force Majeure Events, and damage to the Project, to the extent provided in Section 10.8; and (c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3. 10.3.1.2 DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Appears in 6 contracts
Samples: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement
Eligible Changes. 10.3.1.1 10.3.1.1. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, Force Majeure Events, Events and damage to the ProjectNon- Discriminatory X&X Changes, to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 10.3.1.2. DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA COMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Appears in 4 contracts
Samples: Comprehensive Maintenance Agreement, Comprehensive Maintenance Agreement, Comprehensive Maintenance Agreement
Eligible Changes. 10.3.1.1 10.3.1.1. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, Force Majeure Events, Events and damage to the ProjectNon- Discriminatory Changes, to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 10.3.1.2. DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Appears in 3 contracts
Samples: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement
Eligible Changes. 10.3.1.1 DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, and Force Majeure Events, and damage to the Project, Events to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Appears in 2 contracts
Samples: Capital Maintenance Agreement, Capital Maintenance Agreement
Eligible Changes. 10.3.1.1 10.3.1.1. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, Force Majeure Events, Events and damage to the ProjectNon- Discriminatory O&M Changes, to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 10.3.1.2. DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA COMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Appears in 1 contract
Samples: Comprehensive Maintenance Agreement