Eligible Changes. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows: (a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal; (b) additional costs relating to Force Majeure Events, Hazardous Materials, Non- Discriminatory Changes and Damage to the Project, to the extent provided in Section 4.5.11; and (c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.9.1.2.
Appears in 3 contracts
Samples: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement
Eligible Changes. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Force Majeure Events, Hazardous Materials, Non- Discriminatory Changes Force Majeure Events and Damage to the Project, to the extent provided in Section 4.5.114.5.11.3; and
(c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.9.1.2.
Appears in 1 contract
Samples: Capital Maintenance Agreement