Common use of Emergencies Clause in Contracts

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.

Appears in 186 contracts

Samples: Contract for Services, Contract for Services, Contract for Services

AutoNDA by SimpleDocs

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time time, if any, claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work7 and Article 15.

Appears in 26 contracts

Samples: Contract for Construction, Contract for Construction, Construction Contract

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 16 contracts

Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work15 and Article 7.

Appears in 13 contracts

Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Standard Form of Agreement Between Owner and Contractor, Construction Contract

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Workthis Agreement.

Appears in 12 contracts

Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work15 and Article 7.

Appears in 9 contracts

Samples: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Construction Manager as Constructor

Emergencies. 10.3.1 11.5.1 In any emergency affecting the safety of persons or property, the Contractor shall act promptly act, at its discretion, to prevent threatened damage, injury or loss. Any additional compensation increase in the Contract Price or extension Contract Time(s) of time performance or both claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Workthis Section.

Appears in 7 contracts

Samples: Standard Form Agreement, Construction Services Agreement, Job Order Contract

Emergencies. 10.3.1 10.6.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 5 contracts

Samples: General Conditions of the Contract for Construction, General Conditions of the Contract for Construction, Lease Agreement (Immunicon Corp)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.

Appears in 4 contracts

Samples: Contract Amendment, Service Agreement, Contract Amendment

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 4 contracts

Samples: Construction Contract (Digex Inc/De), Construction Contract (Digex Inc/De), Owner/Contractor Agreement (Altera Corp)

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's sole discretion, to prevent any threatened damage, injury or loss. Any additional Additional compensation or extension of time Contract Time claimed by the Contractor on account because of an emergency work shall will be determined reviewed as provided in Article 12 for Changes in the WorkSection 8.

Appears in 3 contracts

Samples: Standard Agreement, Standard Agreement, Standard Agreement

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work15 and Article 7.

Appears in 3 contracts

Samples: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at their discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of because emergency work shall be determined as provided in Article 12 for Changes in the Work.

Appears in 3 contracts

Samples: Standard Form of Agreement for Facilities Projects, Standard Form of Agreement for Facilities Projects, Standard Form of Agreement for Facilities Projects

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 14.00 for Changes in the Work.

Appears in 3 contracts

Samples: Bid Specifications and Standard Agreement for Construction Services, Bid Specifications and Standard Agreement for Traffic Signal Construction, Bid Specifications and Standard Agreement

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at its discretion, to prevent threatened damage, injury injury, or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work an emergency, not occasioned in whole or in part by Contractor’s acts or omissions or by other causes which are Contractor’s responsibility or related to an indemnity obligation hereunder, shall be determined as provided in Article 12 for Changes in the Work12.

Appears in 3 contracts

Samples: Design Build Agreement, Progressive Design Build Agreement, Construction Agreement

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, property the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.

Appears in 2 contracts

Samples: Agreement Between Owner and Contractor, Agreement Between Owner and Contractor

Emergencies. 10.3.1 13.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in by the Workapplicable provisions of the Contract Documents.

Appears in 2 contracts

Samples: Guaranteed Maximum Price Agreement, Construction Manager at Risk Agreement

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at its discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in accordance with Article 12 for Changes in the Work11, hereof.

Appears in 2 contracts

Samples: Construction Agreement, Construction Agreement

Emergencies. 10.3.1 9.4.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation increase in the Guaranteed Maximum Price or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Workthis Article.

Appears in 2 contracts

Samples: Design Build Agreement (Soy Energy, LLC), Design Build Agreement (Soy Energy, LLC)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in by the Workapplicable provisions of the Contract Documents.

Appears in 2 contracts

Samples: Contract and General Conditions, Contract and General Conditions

Emergencies. 10.3.1 In any an emergency affecting the safety safety, health, or security of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 2 contracts

Samples: Construction Contract, Contract

Emergencies. 10.3.1 10.3.1. In any an emergency affecting the safety of persons or property, the Contractor shall act act, at Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 2 contracts

Samples: Owner Contractor Construction Agreement (Bluerock Residential Growth REIT, Inc.), Owner Contractor Construction Agreement (Bluerock Residential Growth REIT, Inc.)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury injury, or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.

Appears in 1 contract

Samples: City Contractor Agreement

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the WorkParagraph 10 and Paragraph 13.

Appears in 1 contract

Samples: Construction Manager Agreement

Emergencies. 10.3.1 10.5.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s discretion, to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Construction Contract

Emergencies. 10.3.1 10.4.1 In any an emergency affecting the safety of persons or property, the XXXX Contractor shall act use its best efforts to prevent threatened damage, injury or of loss. Any additional Additional compensation or extension of time claimed by the XXXX Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Contract for Construction Manager at Risk

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 13.00 for Changes in the Work.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraphs 4.2 and 8.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Construction Contract (National Instruments Corp /De/)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 section 16 for Changes changes in the Workwork.

Appears in 1 contract

Samples: Contract for Construction or Installation Work

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Section 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Lease (NightHawk Biosciences, Inc.)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury injury, or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 14.00 for Changes in the Work.

Appears in 1 contract

Samples: Bid Specifications and Standard Agreement

Emergencies. 10.3.1 In any emergency an emergency, affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Paragraph 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Construction Contract (Symantec Corp)

Emergencies. 10.3.1 10.6.1 In any an emergency affecting the safety of persons or property, the Contractor shall act use its best efforts to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.time

Appears in 1 contract

Samples: Construction Manager at Risk Agreement

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work15 and Article 7.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor (STAMPS.COM Inc)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act at their discretion to prevent threatened damage, injury or loss. Any additional compensation increase in the Contract Price or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work8.

Appears in 1 contract

Samples: Construction Project Agreement

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act at its discretion, to prevent threatened damage, injury or loss. Any additional compensation increase in the Guarantee Maximum Price or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work10.

Appears in 1 contract

Samples: Contractor Services Agreement

Emergencies. 10.3.1 6.4.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at its reasonable discretion, to prevent threatened damage, injury or loss. Any additional compensation increase in the Contract Sum or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Workthis Article.

Appears in 1 contract

Samples: Sitework Contract (First United Ethanol LLC)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at its discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work work, not occasioned in whole or in part by Contractor’s acts or omissions or by other causes which are Contractor’s responsibility or indemnity obligation hereunder, shall be determined as provided in Article 12 for Changes in the Workhereof.

Appears in 1 contract

Samples: Construction Agreement

Emergencies. 10.3.1 § 10.6.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Section 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Construction Contract (Sierra Pacific Resources /Nv/)

Emergencies. 10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act act, at his discretion, to prevent threatened damage, injury injury, or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 15 for Changes changes in the Workwork.

Appears in 1 contract

Samples: Construction Contract

Emergencies. 10.3.1 10.4.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor’s reasonable discretion to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Section 4.3 and Article 12 for Changes in the Work7.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor (Adicet Bio, Inc.)

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Work15 and Article 7.

Appears in 1 contract

Samples: Fixed Price Construction Contract

Emergencies. 10.3.1 10.6.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work.an

Appears in 1 contract

Samples: General Conditions of the Contract for Construction

Emergencies. 10.3.1 In any an emergency affecting the safety of persons or property, the Contractor shall act act, at Contractor’s discretion, to prevent threatened damage, injury injury, or loss. Any additional Additional compensation or extension of time claimed by the Contractor on account of an emergency work shall be determined as provided in Article 12 for Changes in the Workand agreed to by Broward Health.

Appears in 1 contract

Samples: Contract for Exterior Painting & Pressure Washing