Equipment Changes. a. During Decision Point I, Project Developer may modify its Interconnection Request for updated equipment data. Project Developer shall submit machine modeling data as specified in the PJM Manuals before the close of Decision Point I. Tariff, Part VII, Subpart D, section 310 Phase II
Appears in 4 contracts
Samples: Generation Interconnection Agreement, Generation Interconnection Agreement, Generation Interconnection Agreement
Equipment Changes. a. During Decision Point I, Project Developer may modify its Interconnection Request for updated equipment data. Project Developer shall submit machine modeling data as specified in the PJM Manuals before the close of Decision Point I. Tariff, Part VII, Subpart DD.4, section 310 Phase II
Appears in 1 contract
Samples: Generation Interconnection Agreement
Equipment Changes. a. a1. During Decision Point I, Project Developer may modify its Interconnection Request for updated equipment data. Project Developer shall submit machine modeling data as specified in the PJM Manuals before the close of Decision Point I. Tariff, Part VII, Subpart DD.4, section 310 Phase II
Appears in 1 contract
Samples: Generation Interconnection Agreement
Equipment Changes. a. During Decision Point I, Project Developer may modify its Interconnection Request for updated equipment data. Project Developer shall submit machine modeling data as specified in the PJM Manuals before the close of Decision Point I. Tariff, Part VIIVIII, Subpart DC.4, section 310 407 Phase II
Appears in 1 contract
Samples: Generation Interconnection Agreement
Equipment Changes. a. 1.a.During Decision Point I, Project Developer may modify its Interconnection Request for updated equipment data. Project Developer shall submit machine modeling data as specified in the PJM Manuals before the close of Decision Point I. Tariff, Part VII, Subpart DD.4, section 310 Phase II
Appears in 1 contract
Samples: Generation Interconnection Agreement