Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 90 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 15 contracts
Samples: Draft Contract Agreement, nhidcl.com, nhidcl.com
Examination of work before covering up. In respect of the work which the Authority’s Authority Engineer is entitled to examine, inspect, measure and/or or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Authority Engineer whenever any such work is ready and before it is covered up. The Authority’s Authority Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Authority Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Authority Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Authority Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Authority Engineer, the Contractor shall be entitled to assume that the Authority’s Authority Engineer would not undertake the said inspection.
Appears in 11 contracts
Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction
Examination of work before covering up. In respect of the work which the Authority’s Authority‟s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Authority‟s Engineer whenever any such work is ready and before it is covered up. The Authority’s Authority‟s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Authority‟s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ days‟ notice, to the Authority’s Authority‟s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Authority‟s Engineer within a period of 3 (three) business days from the date on which the Contractor’s Contractor‟s notice hereunder is delivered to the Authority’s Authority‟s Engineer, the Contractor shall be entitled to assume that the Authority’s Authority‟s Engineer would not undertake the said inspection.
Appears in 7 contracts
Samples: Procurement and Construction, Procurement and Construction Agreement, Construction Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 6 contracts
Samples: Model Agreement, Model Agreement, Procurement and Construction Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is works placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer wheneveranysuchworkisreadyandbeforeitiscoveredup.TheAuthority’sEngineer shall then Drafit Contract Agreement either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 5 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is workis placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer wheneveranysuchworkisreadyandbeforeitiscoveredup.TheAuthority’sEngineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspectionsaidinspection.
Appears in 4 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Employer's Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Employer's Engineer whenever any such work is ready and before it is covered up. The Authority’s Employer's Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Employer's Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ ' notice, to the Authority’s Employer's Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Employer's Engineer within a period of 3 (three) business days from the date on which the Contractor’s 's notice hereunder is delivered to the Authority’s Employer's Engineer, the Contractor shall be entitled to assume that the Authority’s Employer's Engineer would not undertake the said inspection.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Procurement and Construction
Examination of work before covering up. In respect of the work which the AuthorityEmployer’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the AuthorityEmployer’s Engineer whenever any such work is ready and before it is covered up. The AuthorityEmployer’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the AuthorityEmployer’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the AuthorityEmployer’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the AuthorityEmployer’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the AuthorityEmployer’s Engineer, the Contractor shall be entitled to assume that the AuthorityEmployer’s Engineer would not undertake the said inspection.
Appears in 2 contracts
Samples: And Construction Agreement, Contract Agreement for Design and Construction
Examination of work before covering up. In respect of the work which the Authority’s 's Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s 's Engineer whenever any such work is ready and before it is covered up. The Authority’s 's Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s 's Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ ' notice, to the Authority’s 's Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s 's Engineer within a period of 3 (three) business days from the date on which the Contractor’s 's notice hereunder is delivered to the Authority’s 's Engineer, the Contractor shall be entitled to assume that the Authority’s 's Engineer would not undertake the said inspection.
Appears in 2 contracts
Samples: Draft Contract Agreement, nhidcl.com
Examination of work before covering up. In respect of the work which the Authority’s Independent Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor Concessionaire shall give notice to the Authority’s Authority and the Independent Engineer whenever any such work is ready and before it is covered up. The Authority’s Authority and the Independent Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor Concessionaire that the Authority’s Independent Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor Concessionaire shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Authority and the Independent Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor Concessionaire receives no response from the Authority’s Authority or the Independent Engineer within a period of 3 (three) business days from the date on which the ContractorConcessionaire’s notice hereunder is delivered to the Authority’s Independent Engineer, the Contractor Concessionaire shall be entitled to assume that the Authority’s Independent Engineer would not undertake the said inspection.
Appears in 2 contracts
Samples: Escrow Agreement, Draft Concession Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is works placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 2 contracts
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is works placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer wheneveranysuchworkisreadyandbeforeitiscoveredup.TheAuthority’sEngineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 2 contracts
Samples: Contract Agreement, Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor Concessionaire shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor Concessionaire that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor Concessionaire shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor Concessionaire receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the ContractorConcessionaire’s notice hereunder is delivered to the Authority’s Engineer, the Contractor Concessionaire shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 2 contracts
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, 47 measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 2 contracts
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.. Draft Contract Agreement 58
Appears in 1 contract
Samples: Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Authority‟s Engineer is entitled to examine, inspect, measure and/or or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor Concessionaire shall give notice to the Authority’s Authority‟s Engineer whenever any such work is ready and before it is covered up. The Authority’s Authority‟s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor Concessionaire that the Authority’s Authority‟s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor Concessionaire shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ days‟ notice, to the Authority’s Authority‟s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor Concessionaire receives no response from the Authority’s Authority‟s Engineer within a period of 3 (three) business days from the date on which the Contractor’s Concessionaire‟s notice hereunder is delivered to the Authority’s Authority‟s Engineer, the Contractor Concessionaire shall be entitled to assume that the Authority’s Authority‟s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Concession Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible pos- sible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered deliv- ered to the Authority’s Engineer, the Contractor shall be entitled to assume that the AuthorityAu- thority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Draft Contract Agreement
Examination of work before covering up. In respect of the work which the AuthorityEmployer’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the AuthorityEmployer’s Engineer whenever any such work is ready and before it is covered up. The AuthorityEmployer’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the AuthorityEmployer’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the AuthorityEmployer’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the AuthorityEmployer’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the AuthorityEmployer’s Engineer, the Contractor shall be entitled to assume that the AuthorityEmployer’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Contract Agreement
Examination of work before covering up. In respect of the work which the AuthoritySPV’s Engineer is entitled to examine, inspect, measure and/or or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the AuthoritySPV’s Engineer whenever any such work is ready and before it is covered up. The AuthoritySPV’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the AuthoritySPV’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the AuthoritySPV’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the AuthoritySPV’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the AuthoritySPV’s EngineerEngineer , the Contractor shall be entitled to assume that the AuthoritySPV’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: www.nicdc.in
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is workis placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer wheneveranysuchworkisreadyandbeforeitiscoveredup.TheAuthority’sEngineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Draft Contract Agreement
Examination of work before covering up. In respect of the work which the AuthorityEmployer’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the AuthorityEmployer’s Engineer whenever any such work is ready and before it is covered up. The AuthorityEmployer’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the AuthorityEmployer’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the then Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the AuthorityEmployer’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the AuthorityEmployer’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the AuthorityEmployer’s Engineer, the Contractor shall be entitled to assume that the AuthorityEmployer’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Epc Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is works placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer wheneveranysuchworkisreadyandbeforeitiscoveredup.TheAuthority’sEngineer shall then Draft Contract Agreement either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure measure, and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection inspection, or testing without unreasonable delay, delay or promptly give notice to the Contractor that the Authority’s Engineer does is not require required to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: bridgecorporationltd.com
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereonxxxxxxx, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: Draft Contract Agreement
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed isplaced thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out carryout the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent orprudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three3(three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or measurementor test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder here under is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the AuthoritytheAuthority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: nhidcl.com
Examination of work before covering up. In respect of the work which the Authority’s Employer‟s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Employer‟s Engineer whenever any such work is ready and before it is covered up. The Authority’s Employer‟s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Employer‟s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ days‟ notice, to the Authority’s Employer‟s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Employer‟s Engineer within a period of 3 (three) business days from the date on which the Contractor’s Contractor‟s notice hereunder is delivered to the Authority’s Employer‟s Engineer, the Contractor shall be entitled to assume that the Authority’s Employer‟s Engineer would not undertake the said inspection.
Appears in 1 contract
Examination of work before covering up. In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ days‟ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.
Appears in 1 contract
Samples: And Construction)